Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96
Section 33.1
Interpretation and disputes
Cite as Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96, s. 33.1 · last amended March 30, 2022 · read from BC Laws on November 17, 2026
The text
(1) In this Division:
“conciliator” means a person appointed as both mediator and arbitrator under subsection (8);
“fairness objection” means the inclusion in an objection to a forestry revitalization proposal under section 33.4 by an impacted contractor of notice that the contractor believes the requirements of section 33.22 (h) have not been met in respect of that contractor and the reasons why the requirements have not been met;
“group of licences” means a group of licences as defined in section 1 of the Forestry Revitalization Act except that, if licences shown for a group of licences in Schedule 1 to the Act have been eliminated or have been added to licences shown for another group of licences in Schedule 1 to the Act through
(a) the acquisition of one or more licence holders by another licence holder,
(b) the amalgamation of two or more licence holders, or
(c) the transfer of licences,
the group of licences must reflect that elimination or addition;
“impacted contractor” means, in respect of a forestry revitalization proposal, a contractor with a replaceable contract in which the parties have specified the amount of work
(a) as a percentage of the total amount of that type of work under the licence, or licences in a fibre basket agreement, to which the contract pertains, and the licence holder proposes to reduce that percentage,
(b) as a fixed amount, and the licence holder proposes to reduce the fixed amount of work by more than the percentage reduction under the Forestry Revitalization Act in the allowable annual cut of the licence, or licences in a fibre basket agreement, to which the contract pertains, or
(c) in a manner other than as described in paragraph (a) or (b), and the licence holder proposes to reduce the amount of work by more than the percentage reduction under the Forestry Revitalization Act in the allowable annual cut of the licence, or licences in a fibre basket agreement, to which the contract pertains;
“licence holder” means all licence holders for a group of licences or an ungrouped licence;
“minimum replaceable contract proportion” means the replaceable contract proportion for
(a) a group of licences immediately before the order of the minister under section 3 (2) of the Forestry Revitalization Act made in relation to the group of licences, or
(b) an ungrouped licence on March 31, 2003;
“proportionate reduction” means the apportionment of the effect of
(a) an order of the minister under section 3 (2) of the Forestry Revitalization Act, for a group of licences, and
(b) that Act, for an ungrouped licence, such that the amount of work to be performed under each replaceable contract that pertains to a licence or licences in a fibre basket agreement, other than a contract that is subject to a seniority system, is reduced by a percentage equal to A − BA × 100 where A is the allowable annual cut of the licence, or licences in a fibre basket agreement, that the replaceable contract pertains to immediately before any reduction in allowable annual cut to that licence or licences under the Forestry Revitalization Act, and B is the allowable annual cut of the licence, or licences in a fibre basket agreement, that the replaceable contract pertains to immediately following all reductions in allowable annual cut to that licence or licences under the Forestry Revitalization Act;
“rejection threshold”, when used in relation to contractors who have replaceable contracts that pertain to those licences included by a licence holder in a forestry revitalization proposal, means objection by either
(a) more than one third of those contractors, or
(b) sufficient of those contractors that they have in aggregate greater than one third of the aggregate amount of work to be performed under all replaceable contracts that pertain to the licences, in which the amount of work to be performed under each contract is determined with regard to the phase contribution amounts for the phases included in that contract;
“replaceable contract proportion” means, at any given time for an ungrouped licence or a group of licences, the proportion determined by the formula A/B where A is the aggregate amount of work, to be performed under all replaceable contracts pertaining to that ungrouped licence or group of licences having regard to the phase contribution amounts for phases under each contract, and B is the allowable annual cut of that ungrouped licence or the aggregate of the allowable annual cuts of the group of licences;
“ungrouped licence” means an ungrouped licence as defined in section 1 of the Forestry Revitalization Act.
(2) For the purposes of determining if a rejection threshold under section 33.41 (2) has been achieved, a replaceable contract does not include a contract for hauling if
(a) the amount of work is specified in the contract with reference to a seniority system, or the work available to the contractor is otherwise subject to a seniority system,
(b) the seniority system is not changed by a forestry revitalization proposal, and
(c) the licence, or licences in a fibre basket agreement, to which the seniority system pertains must not be affected by a forestry revitalization proposal in a manner that would reduce the total amount of work available to the group of contractors in the seniority system any more than would have occurred under proportionate reduction.
(3) If a contractor who has a replaceable contract with a licence holder disagrees with the licence holder on the interpretation or application of any part of this Division, including
(a) the definition of "impacted contractor" and whether a contractor is an impacted contractor,
(b) the definition of "minimum replaceable contract proportion" and the determination of that proportion,
(c) the definition of "replaceable contract proportion" and the determination of that proportion,
(d) the definition of "proportionate reduction" and the calculation of reductions to contracts under a proportionate reduction,
(e) the definition of "rejection threshold" and whether a rejection threshold has been properly determined in respect of a forestry revitalization proposal, or
(f) section 33.41 and whether a forestry revitalization proposal has been accepted or rejected,
the contractor may, by written notice to the licence holder, commence a dispute.
(4) If any provision in this Division requires either a licence holder or a contractor who has a replaceable contract with that licence holder to do something or not to do something, and the licence holder or contractor contravenes that requirement,
(a) any contractor, if the licence holder has contravened the requirement, or
(b) the licence holder, if a contractor has contravened the requirement,
may, by written notice to the other party, commence a dispute.
(5) If a dispute has been commenced in respect of those matters described in subsection (3) (b) or (c), all contractors who have replaceable contracts with the licence holder are parties to the dispute.
(6) If a dispute has been commenced in respect of a matter described in subsection (3) (d), all contractors who have replaceable contracts that pertain to the licence that is subject to proportionate reduction are parties to the dispute.
(7) If a dispute has been commenced in respect of those matters described in subsection (3) (e) or (f), all contractors who have replaceable contracts that pertain to a licence included in the forestry revitalization proposal are parties to the dispute.
(8) All disputes under this Division must be resolved by mediation and arbitration under the system established in Division 2 of Part 4 subject to sections 33.5 and 33.51 and to the following:
(a) within 7 days of the commencement of a dispute the licence holder must notify each contractor that is a party to the dispute as to the person the licence holder proposes to appoint as a conciliator to resolve the dispute;
(b) if there is more than one contractor that is a party to the dispute, the notice under paragraph (a) must list each contractor;
(c) within 7 days of receiving a notice under paragraph (a), a contractor may, by written notice to the licence holder, object to the appointment of the conciliator proposed by the licence holder;
(d) if one third or fewer contractors who are parties to the dispute object under paragraph (c) to the conciliator proposed by the licence holder, that person is the conciliator for the dispute;
(e) if more than one third of the contractors who are parties to the dispute object under paragraph (c) to the conciliator proposed by the licence holder, or if the licence holder fails to give notice under paragraph (a), any party to the dispute, by written notice to the other parties and to the minister, may request the minister to appoint a conciliator;
(f) within 7 days of receiving a request under paragraph (e) to appoint a conciliator, the minister must appoint a registered mediator or a registered arbitrator to act as conciliator;
(g) mediation and arbitration proceedings must be conducted by the conciliator described in paragraph (d) or appointed under paragraph (f);
(h) the person appointed as the conciliator for a dispute deemed to exist with respect to a particular forestry revitalization proposal must act as conciliator in respect of all disputes that arise with respect to the ungrouped licence or group of licences to which the forestry revitalization proposal pertains.
(9) A notice given or delivered under this Division must be given or delivered in accordance with section 8 (13) (b).
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗
Made under Forest Act, RSBC 1996, c. 157.