Asphalt Plant Regulation, B.C. Reg. 217/97

Section 6

Monitoring requirements

Cite as Asphalt Plant Regulation, B.C. Reg. 217/97, s. 6 · last amended October 28, 2019 · read from BC Laws on November 17, 2026

The text

(1) Stack monitoring on each machine train unit discharge must be performed in accordance with the requirements of the Stationary Air Emissions Testing section in the latest version of the Field Sampling Manual issued by the ministry. (2) Stack monitoring must be performed when required by a director and with the hot-in-place asphalt recycling plant operating at its maximum production rate as submitted under section 3 (2) (h). (3) The following information must be collected when performing stack monitoring: (a) discharge flow rate for each machine train unit in cubic metres per minute, corrected to 20C (68F) and 101.325 kPa (1 atmosphere); (b) carbon dioxide and oxygen concentration leaving the exhaust stack of each machine train unit in percent by volume; (c) moisture content of the flue gas for each machine train unit; (d) for a direct fired infrared heating plant, the afterburner combustion temperature for each machine train unit in degrees Celsius, recorded every 15 minutes during sampling; (e) for a hot air recirculating plant, the central combustion chamber temperature for each machine train unit in degrees Celsius, recorded every 15 minutes during sampling; (f) the emission levels of those parameters as specified in Column 1 of Schedule A in the concentration and production units set out opposite in Columns 2 and 3; (g) average plant speed in metres per hour; (h) average plant production rate in square metres of pavement recycled per hour and converted to tonnes of pavement recycled per hour. (4) The completed information required by subsection (3) must, within 60 days after the actual testing, be submitted to the director.
Read the Asphalt Plant Regulation on BC Laws ↗

Made under Environmental Management Act, SBC 2003, c. 53.