Asphalt Plant Regulation, B.C. Reg. 217/97
Section 13
Monitoring requirements
Cite as Asphalt Plant Regulation, B.C. Reg. 217/97, s. 13 · last amended October 28, 2019 · read from BC Laws on November 17, 2026
The text
(1) Stack monitoring on each hot mix asphalt plant aggregate dryer discharge must be performed
(a) as required by subsections (1.1) or (1.2),
(b) when the plant is operating at 80% or more of maximum plant production rate as submitted in the application for registration under section 3 (2) (h) or as authorized by a director, and
(c) in accordance with the requirements of the Stationary Air Emissions Testing section in the latest version of the Field Sampling Manual issued by the ministry.
(1.1) Stack monitoring must be performed
(a) subject to paragraph (b), once in each calendar year, or
(b) once in every second calendar year
(i) for a plant that produced 10,000 tonnes or more of hot mix asphalt in the previous calendar year, if the 3 most recent annual stack monitoring results for the plant comply with the concentration limits for the discharge of emissions set out in Schedule B, or
(ii) for a plant that produced less than 10,000 tonnes of hot mix asphalt in the previous calendar year.
(1.2) A director may require that stack monitoring be performed if the director has reason to believe that
(a) discharged emissions have exceeded or may exceed the concentration limits set out in Schedule B, or
(b) the stack monitoring has not been conducted in accordance with subsection (1) (c).
(2) Repealed. [B.C. Reg. 357/2002, s. 4 (d).]
(3) The following information must be collected when performing stack monitoring:
(a) flue gas discharge flow rate in cubic metres per minute, corrected to 20C (68F) and 101.325 kPa (1 atmosphere);
(b) carbon dioxide and oxygen concentrations in flue gas in percent by volume;
(c) moisture content of flue gas;
(d) the emission levels for those parameters in the units specified in Schedule B;
(e) amount of recycled asphalt pavement used, if any, as a percentage of total hot mix asphalt production;
(f) temperature of the final hot mix asphalt product leaving the plant;
(g) plant production rate measured over the duration of stack monitoring expressed in tonnes per hour;
(h) emission rate for particulates, organics and carbon monoxide in Schedule B expressed as grams per tonne of hot mix asphalt produced.
(4) Repealed. [B.C. Reg. 357/2002, s. 4 (d).]
(5) Complete stack monitoring results must, within 60 days of the actual testing, be submitted to the director.
(6) For new plants, stack monitoring must be performed to demonstrate compliance within 30 working days of any operation of the plant.
Read the Asphalt Plant Regulation on BC Laws ↗
Made under Environmental Management Act, SBC 2003, c. 53.