Emergency Management Regulation, B.C. Reg. 217/2017
Schedule B
Schedule B
Cite as Emergency Management Regulation, B.C. Reg. 217/2017, Schedule B · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
Schedule B
(section 7)
Well Distances
Hazard planning distances for wells are determined by reference to the maximum potential hydrogen sulphide (H2S) release rates from a well during disposal, drilling, completion, re-completion or production operations.
H2S Release Rates
Disposal operations
The maximum potential H2S release rates during disposal operations must be determined using the maximum reservoir pressure value set out in the order, made under section 75 of the Act, designating the disposal well as a special project for disposal operations.
Drilling operations
The maximum potential H2S release rates during drilling operations must be determined as follows: 1 For a proposed well, the maximum gas rate (AOF) values and maximum H2S concentrations for each H2S-bearing formation must be determined for each of at least 5 wells drilled and tested in an analogous geological area or pool within 5 km of the proposed well. 2 The H2S release rates for all potential H2S-bearing formations in the proposed well must be determined based on the highest AOF and highest H2S concentration for each formation and the sum of the H2S release rates for all the formations that will be open to the well bore during drilling operations. 3 If appropriate data does not exist or is otherwise inadequate, the hazard planning distance is 3 km.
Completion or re-completion operations
For completion or re-completion operations in an existing well, data from the appropriate formation in the well must be used to determine H2S release rates, but if the appropriate data does not exist or is otherwise inadequate, H2S release rates must be determined in accordance with the equations and notes set out below for production operations.
Production operations
The maximum potential H2S release rates during production operations must be determined in accordance with the following equation and the notes that follow: H2S Release Rate = H2S% x AOF8 640 000 where H2S% = volume of H2S expressed as a percentage of the total volume of gas; AOF = maximum gas rate (m3/d).
Notes: 1 For gas wells, if an AOF test has been conducted and value determined for a formation in a well, that value must be used. If an AOF test value has not been determined, a theoretical AOF must be calculated using the following formula: AOF = Gas Test Rate x Pr2(Pr2 - Pf2) where AOF = maximum gas rate (m3/d); Gas Test Rate = gas flow rate during testing (m3/d); Pr = reservoir pressure (kPa). Pf = flowing bottom hole pressure (kPa); 2 For oil wells, the AOF must be calculated using the following formula: AOF = Oil Test Rate x GOR[1 — 0.2 x (Pf/Pr) — 0.8 x (Pf/Pr)2] where AOF = maximum gas rate (m3/d); Oil Test Rate = oil flow rate during testing (m3/d); GOR = gas-oil ratio from oil test rate well (m3/m3); Pf = flowing bottom hole pressure (kPa); Pr = reservoir pressure (kPa).
Determination of Well Distances
The hazard planning distance for wells is the distance indicated on the vertical axis of Chart B that corresponds to the release rate indicated on the horizontal axis of the chart, as indicated by the graphline on the chart.
Chart B: Well Distances
Read the Emergency Management Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.