Forest Planning and Practices Regulation, B.C. Reg. 14/2004
Section 35
Soil disturbance limits
Cite as Forest Planning and Practices Regulation, B.C. Reg. 14/2004, s. 35 · last amended January 1, 2026 · read from BC Laws on November 17, 2026
The text
(1) In this section:
“first agreement holder” means an agreement holder that is not a fibre recovery tenure holder;
“roadside work area” means the area adjacent to a road where one or both of the following are carried out:
(a) decking, processing or loading timber;
(b) piling or disposing of logging debris;
“sensitive soils” means soils that, because of their slope gradient, texture class, moisture regime, or organic matter content have the following risk of displacement, surface erosion or compaction:
(a) for the Interior, a very high hazard;
(b) for the Coast, a high or very high hazard.
(2) Repealed. [B.C. Reg. 580/2004, s. 30 (a).]
(3) An agreement holder other than a holder of a minor tenure or a fibre supply licence to cut, which holder is carrying out timber harvesting, must not cause the amount of soil disturbance on the net area to be reforested to exceed the following limits:
(a) if the standards unit is predominantly comprised of sensitive soils, 5% of the area covered by the standards unit, excluding any area covered by a roadside work area;
(b) if the standards unit not is not predominantly comprised of sensitive soils, 10% of the area covered by the standards unit, excluding any area covered by a roadside work area;
(c) 25% of the area covered by a roadside work area.
(4) An agreement holder may cause soil disturbance that exceeds the limits specified in subsection (3) if the holder
(a) is removing infected stumps or salvaging windthrow and the additional disturbance is the minimum necessary, or
(b) is constructing a temporary access structure and both of the following apply:
(i) the limit set out in subsection (3) (a) or (b), as applicable, is not exceeded by more than 5% of the area covered by the standards unit, excluding the area covered by a roadside work area;
(ii) before the regeneration date, a sufficient amount of the area within the standards unit is rehabilitated such that the agreement holder is in compliance with the limits set out in subsection (3).
(4.1) Despite subsections (3) and (4), if a first agreement holder is authorized to carry out timber harvesting in an area and a fibre recovery tenure holder is authorized to carry out timber harvesting in an area that overlaps with the area of the first agreement holder, the agreement holders must not cause the cumulative amount of soil disturbance from all primary forest activities carried out on the area of overlap to exceed 25% of that area.
(4.2) Subsection (4.1) does not apply in respect of any area of overlap occupied by a permanent access structure.
(5) The minister may require an agreement holder to rehabilitate an area of compacted soil if all of the following apply:
(a) the area of compacted soil
(i) was created by activities of the holder,
(ii) is within the net area to be reforested, and
(iii) is a minimum of 1 ha in size;
(b) the holder has not exceeded the limits described in subsection (3) or the holders have not exceeded the limit described in subsection (4.1), as applicable;
(c) rehabilitation would, in the opinion of the minister,
(i) materially improve the productivity and the hydrologic function of the soil within the area, and
(ii) not create an unacceptable risk of further damage or harm to, or impairment of, forest resource values related to one or more of the subjects listed in section 149 (1) of the Act.
(6) An agreement holder who rehabilitates an area under subsection (4) or (5) must
(a) remove or redistribute woody materials that are exposed on the surface of the area and are concentrating subsurface moisture, to the extent necessary to limit the concentration of subsurface moisture on the area,
(b) de-compact compacted soils, and
(c) return displaced surface soils, retrievable side-cast and berm materials.
(7) If an agreement holder rehabilitates an area under subsection (4) or (5) and erosion of exposed soil from the area would cause sediment to enter a stream, wetland or lake, or a material adverse effect in relation to one or more of the subjects listed in section 149 (1) of the Act, the agreement holder, unless placing debris or revegetation would not materially reduce the likelihood of erosion, must
(a) place woody debris on the exposed soils, or
(b) revegetate the exposed mineral soils.
Read the Forest Planning and Practices Regulation on BC Laws ↗
Made under Forest and Range Practices Act, SBC 2002, c. 69.