Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014
Section 20
Notice of cessation of operations
Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 20 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) An LNG facility permit holder who intends to cease operations on one or more liquefaction trains of production capacity must notify the regulator
(a) subject to paragraph (b), at least 60 days before beginning the cessation process, and
(b) in cases of an emergency, as soon as practicable.
(2) An LNG facility permit holder who has ceased operations on one or more liquefaction trains of production capacity must notify the regulator before resuming liquefaction.
Read the Liquefied Natural Gas Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.