Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 19 · last amended April 1, 2025 · read from BC Laws on November 17, 2026

The text

(1) An LNG facility permit holder must notify the regulator at least 24 hours before a planned flaring event from the LNG facility if the quantity of gas to be flared exceeds 10 000 m3. (2) If an unplanned flaring event occurs at the LNG facility and the quantity of flared gas exceeds 10 000 m3, the LNG facility permit holder must notify the regulator within 24 hours after the flaring event begins. (3) An LNG facility permit holder must maintain a log of all flaring that occurs at the LNG facility and submit flaring information to the regulator on its request.
Read the Liquefied Natural Gas Facility Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.