Minimum Buffer Distances
[section 4 (2)] 1
Structure 2
Non-explosive
energy source
(metres) 3
Explosive energy source Charge
weight
(kg) Distance
(metres) Building or structure with a concrete base, residence, barn, concrete irrigation structure, concrete lined irrigation canal and concrete water pipeline 50 all 180 Artificial water hole, developed spring or piezometer 100 (vibroseis)
50 (other than vibroseis) all 180 Driveway, gateway or buried water pipeline (other than a concrete-lined pipeline) 5 all 10 Buried telephone or telecommunication line 2 all 2 Survey monument 2 all 2 Petroleum or natural gas pipeline (measured from the centre line of the pipeline) and a petroleum or natural gas well 15 > 0 ≤ 2
> 2 ≤ 4
> 4 ≤ 6
> 6 ≤ 8
> 8 ≤ 10
>10 ≤ 20
>20 ≤ 40
>40 ≤ 100 32
45
55
64
72
101
143
226 Piping used to transmit, at less than 700 kPa, natural gas to consumers by a gas utility as defined in the Gas Utility Act 3 all 3 Dugout or other earthen excavation designed to collect runoff and store water for later use, measured from the inside edge of the high water mark 25 all 50 Irrigation canal (other than a concrete-lined canal) 10 all 10 Dam having a storage reservoir capacity of 30 000 cubic meters or more and that is 2.5 meters high or more when measured to the top of the barrier 50 all 180 Cemetery, measured to its surveyed boundary 50 all 100 Domestic septic tank below ground or septic storage device above ground 15 all 15