Geophysical Exploration Regulation, B.C. Reg. 280/2010
Section 5
Hole plugging
Cite as Geophysical Exploration Regulation, B.C. Reg. 280/2010, s. 5 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) Immediately after drilling a shot hole, a geophysical permit holder must plug the shot hole as follows:
(a) the drill cuttings or other material from the hole must be returned to fill the hole;
(b) a plug of a diameter not less than that of the hole must be placed into the hole to a depth of not less than one meter below the surface;
(c) the section above the plug must be filled with a suitable material and firmly tamped to effect a permanent seal;
(d) any surplus soil or other material removed in the drilling of any hole must be spread so as to avoid interference with drainage, and ground contours must be restored as nearly as possible to their original condition.
(2) Despite subsection (1), a geophysical permit holder may use a temporary plug for a hole that has been drilled but into which an explosive has not been placed if the temporary plug prevents the flow of water or gas to the surface and prevents the hole from becoming a hazard to animals or people.
Read the Geophysical Exploration Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.