Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation, B.C. Reg. 104/2004
Section 74
Owner responsible for safety in a plant
Cite as Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation, B.C. Reg. 104/2004, s. 74 · last amended December 31, 2024 · read from BC Laws on November 17, 2026
The text
(1) The owner of a plant must ensure that there is compliance with all of the following:
(a) floors, pits and sumps in the plant have adequate drainage;
(b) the plant or equipment in the plant prevents oil or other liquids harmful to a boiler from being introduced into boiler feedwater;
(c) there is adequate drainage to prevent accumulation of condensate in any piping;
(d) if the plant has an automated control system described in section 6 (l) (i) and (ii), functional testing and maintenance programs for the system are carried out.
(2) If regulated work is being performed on a pressure piping system in a plant, the owner of the plant must ensure that the portion of the pressure piping system where the regulated work is performed is safe for the activity being performed.
(3) If steam from a boiler in a plant exceeds 103 kPa gauge pressure and will be used for services at a lower pressure, the owner of the plant must ensure that, in association with the pressure reducing device,
(a) one or more relief devices or safety valves are provided on the low pressure side of the system, or
(b) the piping and equipment on the low pressure side of the system is designed to withstand the upstream design pressure.
(4) The relief or safety devices referred to in subsection (3) (a) must be located adjoining, or as close as possible to, the reducing valve.
(5) To provide for servicing of the pressure reducing device, hand controlled bypass valves having a capacity no greater than the reducing device may be installed around the pressure reducing device if
(a) the downstream piping is adequately protected by relief or safety devices of proper capacity, or
(b) the design pressure of the downstream piping equipment is at least as high as the design pressure of the upstream piping equipment.
Read the Power Engineers, Boiler, Pressure Vessel and Refrigeration Safety Regulation on BC Laws ↗
Made under Safety Standards Act, SBC 2003, c. 39.