Electrical Safety Regulation, B.C. Reg. 100/2004
Section 19
Inspection of electrical work
Cite as Electrical Safety Regulation, B.C. Reg. 100/2004, s. 19 · last amended March 4, 2025 · read from BC Laws on November 17, 2026
The text
(1) If a person holds an electrical installation permit, the field safety representative named on the permit must request an inspection at least once in every 180 day period.
(2) If no inspection request under subsection (1) has been submitted within a 180 day period, the holder of the permit must have the permit amended to allow for the extra time before performing any regulated work.
(3) On the completion of each phase of electrical work under an installation permit, the field safety representative named on the permit must request an inspection.
(4) A person must not do any of the following unless the regulated work has been inspected or the inspection has been waived:
(a) conceal any portion of the rough wiring;
(b) connect power to the electrical supply system;
(c) if the inspection is required for other than the last phase, work on the next phase of the electrical work.
(5) If an inspection is required for regulated work, other than the regulated work in the last phase, a person must not do regulated work on the next phase of electrical work.
(6) After receiving a request under subsection (1) or (3), the regulatory authority may require
(a) an inspection, or
(b) a declaration that the work performed under the permit complies with the Act and the regulations.