Clean Energy Act, SBC 2010, c. 22
Section 8
Rates
Cite as Clean Energy Act, SBC 2010, c. 22, s. 8 · read from BC Laws on November 17, 2026
The text
(1) In setting rates under the Utilities Commission Act for the authority, the commission must ensure that the rates allow the authority to collect sufficient revenue in each fiscal year to enable it to recover its costs incurred with respect to
(a) the achievement of electricity self-sufficiency, and
(b) a project, program, contract or expenditure referred to in section 7 (1), except
(i) to the extent the expenditure is accounted for in paragraph (a).
(ii) [Repealed 2019-24-5.]
(2) Subject to subsection (1) of this section, the commission must set under the Utilities Commission Act a rate proposed by the authority with respect to the project referred to in section 7 (1) (a) of this Act.
(3) The commission must not, except on application by the authority, cancel, suspend or amend a rate set in accordance with subsection (2).
(4) The authority must provide to the minister, in accordance with the regulations, an annual report comparing the electricity rates charged by the authority with electricity rates charged by public utilities in other jurisdictions in North America, including an assessment of the extent to which the authority's electricity rates continue to be competitive with those other rates.