Clean Energy Act, SBC 2010, c. 22

Section 7

Exempt projects, programs, contracts and expenditures

Cite as Clean Energy Act, SBC 2010, c. 22, s. 7 · read from BC Laws on November 17, 2026

The text

(1) The authority is exempt from sections 45 to 47 and 71 of the Utilities Commission Act to the extent applicable, and from any other sections of that Act that the minister may specify by regulation, with respect to the following projects, programs, contracts and expenditures of the authority, as they may be further described by regulation: (a) the Northwest Transmission Line, a 287 kilovolt transmission line between the Skeena substation and Bob Quinn Lake, and related facilities and contracts; (b) Mica Units 5 and 6, a project to install two additional turbines and related works and equipment at Mica; (c) Revelstoke Unit 6, a project to install an additional turbine and related works and equipment at Revelstoke; (d) Site C, a project to build a third dam on the Peace River in northeast British Columbia to provide approximately (i) 4 600 gigawatt hours of energy each year, and (ii) 900 megawatts of capacity; (e) a bio-energy phase 2 call to acquire up to 1 000 gigawatt hours per year of electricity; (f) one or more agreements with pulp and paper customers eligible for funding under Canada's Green Transformation Program under which agreement or agreements the authority acquires, in aggregate, up to 1 200 gigawatt hours per year of electricity; (g) the clean power call request for proposals, issued on June 11, 2008, to acquire up to 5 000 gigawatt hours per year of electricity from clean or renewable resources; (h) [Repealed 2024-20-1.] (i) [Repealed 2019-24-4.] (j) the actions taken to comply with section 17 (2) and (3); (k) the program described in section 17 (4). (2) The persons and their successors and assigns who enter into an energy supply contract with the authority related to anything referred to in subsection (1) are exempt from section 71 of the Utilities Commission Act with respect to the energy supply contract. (3) The commission must not exercise a power under the Utilities Commission Act in a way that would directly or indirectly prevent the authority from doing anything referred to in subsection (1).
Read the Clean Energy Act on BC Laws ↗