Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations, SOR/2025-88
Section 49
Action plan
Cite as Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations, SOR/2025-88, s. 49 · current to July 24, 2025 · regulation last amended July 5, 2025
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) An operator must develop and implement an action plan before
(a) reducing the level of liquid in a high benzene tank such that its internal floating roof or external floating roof no longer floats at all times on the surface of the liquid;
(b) cleaning the interior of a high benzene tank; or
(c) replacing the primary seal of the internal floating roof or external floating roof of a high benzene tank.
(2) The operator must submit the action plan to the Minister at least 30 days before the day on which the operator intends to implement the plan and the plan must contain the information referred to in Part 3 of Schedule 3.
(3) Within 15 days after the day on which the action plan is received, the Minister must notify the operator in writing if the Minister requires the operator to include conditions in the plan respecting
(a) monitoring;
(b) the repair of a defect of a high benzene tank, internal floating roof, external floating roof or primary seal and the applicable time limits;
(c) the replacement of a primary seal and the applicable time limits;
(d) the use of an internal floating roof, external floating roof or temporary vapour control system or any other emissions control equipment;
(e) the implementation of other VOC emissions reduction measures;
(f) reporting and notification;
(g) record-keeping; and
(h) any other matter, if the Minister considers it necessary for the purposes of these Regulations.
(4) If the Minister requires the operator to include conditions in the action plan under subsection (3), the operator must not implement the action plan until the operator submits a revised action plan to the Minister including those conditions.
(5) Despite the time limit referred to in subsection (2), the operator may implement the action plan if the Minister has notified the operator in writing that they may do so.
(6) The operator must notify the Minister of the completion of any activity referred to in subsection (1) within five days after the day on which the activity is completed.
Read the Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations on the Justice Laws Website ↗
Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.