Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations, SOR/2025-88
Section 106
Reasons
Cite as Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations, SOR/2025-88, s. 106 · current to July 24, 2025 · regulation last amended July 5, 2025
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) The operator of a facility must develop an extended repair plan for a defect of a tank or its internal floating roof or external floating roof if an authorized official determines that the tank needs to be removed from service so that the defect may be repaired but the tank cannot, for one of the following reasons, be removed from service such that the repair can be completed within the applicable time limit set out in section 100:
(a) the tank’s removal from service would require a shutdown of some or all of the petroleum processing equipment at the facility;
(b) there are no options at the facility or elsewhere for the storage, processing, treatment or disposal of the contents of the tank; or
(c) there are significant risks to safety, human health or the environment associated with the tank’s removal from service that would be mitigated with additional repair time.
(2) The extended repair plan must be submitted to the Minister at least 30 days before the applicable time limit set out in section 100 ends and must include the information referred to in Schedule 9.
(3) The Minister may, on receiving the extended repair plan, require that the operator provide any clarifications or additional information.
(4) If, on receiving the extended repair plan, the Minister has reasonable grounds to believe that the date set out in the plan for the tank’s removal from service is later than warranted by the circumstances, the Minister may require that the operator resubmit the plan and change that date to a date specified by the Minister.
(5) The operator must implement the extended repair plan beginning the day after the day on which the applicable time limit set out in section 100 ends and must remove the tank from service within the time limit set out in the extended repair plan.
(6) If an operator implements an extended repair plan for a reason referred to in paragraph (1)(b) or (c), the operator must cease filling the tank with any volatile petroleum liquids beginning on the day after the day on which the applicable time limit set out in section 100 ends.
(7) An operator that implements an extended repair plan must
(a) if there is a change to the information referred to in items 9 to 11 of Schedule 9, update and resubmit the extended repair plan to the Minister as soon as feasible before the change takes effect; and
(b) notify the Minister of the day on which the tank is removed from service within five days after that day.
Read the Reduction in the Release of Volatile Organic Compounds (Storage and Loading of Volatile Petroleum Liquids) Regulations on the Justice Laws Website ↗
Made under Canadian Environmental Protection Act, 1999, S.C. 1999, c. 33.