Canada Offshore Renewable Energy Regulations, SOR/2024-272

Section 20

Application — additional contents

Cite as Canada Offshore Renewable Energy Regulations, SOR/2024-272, s. 20 · current to December 2, 2025 · regulation last amended December 16, 2024

Statute Watch

Get an alert when a bill in Parliament would change this section, and every time it moves.

The text

For the purposes of subsection 298(2) of the Act, an application for authorization to carry on work or activities in relation to the decommissioning and abandonment of facilities, equipment and systems related to an offshore renewable energy project or offshore power line must include, in addition to the information and documents referred to in section 6, (a) a description of any existing infrastructure at the operations site and an explanation of how that infrastructure was taken into account in the planning of the work or activities that are the subject of the application; (b) the results of an assessment of the condition of any facilities, equipment or systems that are to be decommissioned and abandoned; (c) a description of the facilities, equipment and systems to be decommissioned and abandoned in place or decommissioned, removed and disposed of, as the case may be, including, if applicable, the methods to be used to remove and transport them and how and where they are to be disposed of; (d) a risk assessment in respect of the work or activities that are the subject of the application that addresses the safety and security of persons and infrastructure that are at, on or in the vicinity of the facilities, equipment or systems, including an assessment of any risks associated with the operation of vessels, vehicles, aircraft or other conveyances in that vicinity; (e) an environmental and socio-economic assessment in respect of the work or activities that are the subject of the application; (f) an assessment in respect of the work or activities that are the subject of the application that addresses the factors referred to in paragraphs 298(3)(d) and (e) of the Act; (g) a description of the methods to be used to restore the operations site after the decommissioning and abandonment of the facilities, equipment and systems; and (h) an estimate of the costs of the decommissioning and abandonment and an indication of the manner in which the operator will finance or pay for those costs.
Read the Canada Offshore Renewable Energy Regulations on the Justice Laws Website ↗

Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.

Bills in Parliament that would change this section 0

No bill we hold would amend or repeal this section.