The text
For the purposes of subsection 298(9) of the Act, an authorization in relation to the construction, operation and maintenance of facilities, equipment and systems related to an offshore renewable energy project or offshore power line is, in addition to being subject to the conditions set out in sections 7 and 14, subject to the condition that the operator ensure that the following documents and information are submitted to and approved by the Regulator before the authorized work or activities related to operation and maintenance begin:
(a) a description of the finalized version of an integrity management program that meets the requirements set out in section 19;
(b) a preliminary version of the decommissioning and abandonment plan that will be submitted under paragraph 21(a) that builds on the overview referred to in paragraph 13(i);
(c) any updates to the information provided under paragraph 13(j);
(d) a description of the navigational safety zones proposed for the purposes of paragraph 28(1)(a) or a justification of why navigational safety zones are not needed;
(e) the certificate of fitness issued under subsection 44(1) in respect of the facilities, equipment and systems; and
(f) the plan referred to in section 45, prepared by the certifying authority, for the periodic inspection of the facilities, equipment and systems during their operation and maintenance.
Read the Canada Offshore Renewable Energy Regulations on the Justice Laws Website ↗
Made under Canadian Energy Regulator Act, S.C. 2019, c. 28, s. 10.