Grade Crossings Regulations, SOR/2014-275
Section 94
Initial installation
Cite as Grade Crossings Regulations, SOR/2014-275, s. 94 · current to July 24, 2025 · regulation last amended November 26, 2021
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Immediately after the initial installation of a warning system, but before it is placed in service, all of the components of the warning system must be inspected and tested in accordance with article 17.1 of the Grade Crossings Standards.
(2) Immediately after the modification or installation of a component of the warning system, but before the warning system is placed in service, the component and all other components that are directly affected by that modification or installation must be inspected and tested in accordance with article 17.1 of the Grade Crossings Standards.
(3) In the event of severe weather or other environmental conditions that may affect the operation of the warning system or its components, the warning system or the components must be inspected within a reasonable period of time to ensure that they are working properly.
Read the Grade Crossings Regulations on the Justice Laws Website ↗
Made under Railway Safety Act, R.S.C. 1985, c. 32 (4th Supp.).