Wastewater Systems Effluent Regulations, SOR/2012-139
Section 29
General requirements
Cite as Wastewater Systems Effluent Regulations, SOR/2012-139, s. 29 · current to June 14, 2026 · regulation last amended June 4, 2026
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) A holder of a transitional authorization in respect of a wastewater system must, during the period of authorization,
(a) comply with sections 7 to 10, 12 to 14, 16 to 22 and 48; and
(b) implement the plan referred to in subsection 4(1) or paragraphs 25(1)(f) or (s) or, if applicable, the amended plan referred to in subsection (3) — in accordance with its schedule for implementation.
(2) The holder of a transitional authorization must, within 90 days before the following dates, send to the authorization officer a progress report on the steps taken to implement the plan referred to in subsection 4(1) or paragraph 25(1)(f) or (s), as the case may be:
(a) July 1 of 2026, 2028 and 2030, if the period of authorization ends on December 31, 2030; and
(b) July 1 of 2026, 2028, 2030, 2032, 2034, 2036, 2038 and 2040, if the period of authorization ends on December 31, 2040.
(3) The progress report must include amendments to the plan referred to in subsection 4(1) or paragraph 25(1)(f) or (s), as the case may be, along with a schedule to implement the plan.
Read the Wastewater Systems Effluent Regulations on the Justice Laws Website ↗
Made under Fisheries Act, R.S.C. 1985, c. F-14.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.