International Bridges and Tunnels Regulations, SOR/2009-17
Section 11
Cite as International Bridges and Tunnels Regulations, SOR/2009-17, s. 11 · current to March 31, 2026 · regulation last amended March 25, 2026
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
An owner of an international bridge or international tunnel shall submit to the Minister a final report signed and sealed by two engineers, relating to a special condition survey, test or other additional engineering investigation conducted in respect of the bridge or tunnel, other than the evaluation referred to in section 12, within one month after the day on which the report is approved by the owner but not more than six months after the day on which the additional engineering investigation is completed.
Read the International Bridges and Tunnels Regulations on the Justice Laws Website ↗
Made under International Bridges and Tunnels Act, S.C. 2007, c. 1.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.