Dominion Water Power Regulations, C.R.C., c. 1603
Section 11
Cite as Dominion Water Power Regulations, C.R.C., c. 1603, s. 11 · current to July 24, 2025 · regulation last amended August 28, 2019
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) The Director shall examine the general construction plans and specifications of the works and the plan of lands, and shall report thereon to the Minister.
(2) The Director shall notify the interim licensee in writing whether the plans have been approved subject to conditions, or have been rejected and the interim licence cancelled.
(3) Approval or non-approval of any plans shall neither incur the responsibility of the Crown nor relieve the interim licensee from the consequences that may result from the construction of the works, from imperfections in departmental requirements, or from the operation of the works.
Read the Dominion Water Power Regulations on the Justice Laws Website ↗
Made under Dominion Water Power Act, R.S.C. 1985, c. W-4.