Canada Oil and Gas Drilling and Production Regulations, C.R.C., c. 1517
Section 15
Cite as Canada Oil and Gas Drilling and Production Regulations, C.R.C., c. 1517, s. 15 · current to July 24, 2025 · regulation last amended March 22, 2006
Statute Watch
Get an alert when a bill in Parliament would change this section, and every time it moves.
The text
(1) Before abandoning a well drilled under these Regulations and before removing any part of the casing therefrom, the licensee, permittee or lessee shall notify the Oil Conservation Engineer in writing of his intention to so do on a form approved by the Chief in triplicate and shall obtain written approval of such abandonment and removal of casing from the Oil Conservation Engineer but such approval may first be given orally.
(2) In abandoning wells, cement plugs shall be used to protect porous formations and unless otherwise directed by the Oil Conservation Engineer, the plugs shall be felt for in accordance with good oil field practice and new plugs shall be placed when necessary.
(3) The interval between plugs shall be filled with an approved mudladen fluid of proper density unless otherwise directed by the Oil Conservation Engineer.
(4) Seismic shot holes and structure test holes shall be abandoned by a method approved by the Oil Conservation Engineer and in accordance with good oil field practice.
(5) Upon abandonment of the well, all excavations shall be filled and exact locations of such well or hole shall be marked by a pipe not less than two inches in diameter set solidly into a concrete block or other approved material and projecting at least four feet above ground level.
(6) The name of the well shall be plainly and permanently marked on the pipe in a manner approved by the Oil Conservation Engineer.
Read the Canada Oil and Gas Drilling and Production Regulations on the Justice Laws Website ↗
Made under Territorial Lands Act, R.S.C. 1985, c. T-7.
Bills in Parliament that would change this section 0
No bill we hold would amend or repeal this section.