Missouri 2026 Regular Session Status: Enacted 1 R cosponsors

HB 2474 — Modifies provisions governing design-build contracts

Last action — Delivered to Secretary of State (G)

  1. ✓
    Introduced
  2. ✓
    In Committee
  3. ✓
    Passed House
  4. ✓
    Passed Senate
  5. ✓
    To Executive
  6. 6
    Enacted

This bill has been enacted into law. Introduced December 17, 2025. Enacted.

Signed by Governor Mike Kehoe (Republican) on May 28, 2026.

Odds of enactment

High chance

Based on the sponsor, cosponsors, and committee posture, this bill has a high chance of becoming law.

Upgrade to see the exact probability and what's driving it.

A statistical estimate from our own model of past outcomes — an insight, not a guarantee. Policymaking is volatile.

Prognosis

Likely to advance 72% · moderate confidence
  • Enacted

    Current position in the legislative process.

  • 1 sponsor

    1 primary, 0 co-sponsors signed on.

  • Single-party support

    Sponsorship is currently within one party (1 R).

  • Cleared a recorded vote

    Passed 8 recorded votes so far.

Based on stage, sponsorship breadth, committee status, recorded votes, and cross-state momentum — a description of the observable signals, not a prediction.

In plain language

The bill alters rules for design-build contracts in construction projects.

This bill modifies existing rules regarding design-build contracts, which streamline project delivery in construction. It aims to improve efficiency and collaboration between designers and builders.

What this means for you
  • Small Business: This means that small construction firms may find it easier to compete and collaborate on projects under the new rules.

Bill Text

What changed in the latest version

294 added · 336 removed

Plain-language change summary

The bill HB 2474 has undergone a minor change in its drafting process. Specifically, a previous version labeled with "C" has been updated to a "P" version, indicating it has been perfected or finalized for further consideration. This matters because it shows that the bill has been refined and is now in a more polished state, which is an important step in the legislative process before it can be voted on.

→
Previous
Latest
SECOND REGULAR SESSION [TRULY AGREED TO AND FINALLY PASSED] SENATE COMMITTEE SUBSTITUTE FOR HOUSE COMMITTEE SUBSTITUTE FOR HOUSE BILL NO.
SECOND REGULAR SESSION [PERFECTED] HOUSE COMMITTEE SUBSTITUTE FOR HOUSE BILL NO.
2474 103RD GENERAL ASSEMBLY 5233S.05T 2026 AN ACT To repeal sections 34.046 and 67.5060, RSMo, and to enact in lieu thereof two new sections relating to public contracts.
2474 103RD GENERAL ASSEMBLY 5233H.02P JOSEPH ENGLER, Chief Clerk AN ACT To repeal section 67.5060, RSMo, and to enact in lieu thereof one new section relating to design-build contracts.
Sections 34.046 and 67.5060, RSMo, are repealed and two new sections enacted in lieu thereof, to be known as sections 34.046 and 67.5060, to read as follows:
Section 67.5060, RSMo, is repealed and one new section enacted in lieu thereof, to be known as section 67.5060, to read as follows:
34.046.
67.5060.
The commissioner of administration may contract directly with other governmental entities for the purchase of supplies.
The commissioner of administration may also participate in, sponsor, conduct or administer a cooperative purchasing agreement whereby supplies are procured in accordance with a contract established by another governmental entity provided that such contract was established in accordance with the laws and regulations applicable to the establishing governmental entity.
2.
The commissioner of administration may also participate in, sponsor, conduct, or administer a cooperative purchasing agreement with a contract established by a non- profit entity whose membership is exclusively made up of governmental entities and whose governing body is selected or elected exclusively by governmental entities, and where the contract was established in accordance with the laws and regulations applicable to the governmental entities.
Such cooperative purchasing agreement shall be utilized for the purchase of supplies including but not limited to upkeep and maintenance of physical infrastructure.
The commissioner of administration may permit political subdivisions to participate in any cooperative purchasing agreement.
EXPLANATION — Matter enclosed in bold-faced brackets [thus] in the above bill is not enacted and is intended to be omitted from the law.
Matter in bold-face type in the above bill is proposed language.
SCS HCS HB 2474 2 67.5060.
1.
and (b) Noncivil works projects, such as buildings, site improvements, and other structures, habitable or not, commonly designed by architects in excess of [seven] two million five hundred thousand dollars;
and (b) Noncivil works projects, such as buildings, site improvements, and other structures, habitable or not, commonly designed by architects [in excess of seven million dollars];
(4) "Design-builder", any individual, partnership, joint venture, or corporation subject to a qualification-based selection that offers to provide or provides design services and general contracting services through a design-build contract or a progressive design-build contract in which services within the scope of the practice of professional architecture or engineering are performed respectively by a licensed architect or licensed engineer and in which services within the scope of general contracting are performed by a general contractor or other legal entity that furnishes architecture or engineering services and construction services either directly or through subcontracts or joint ventures;
EXPLANATION — Matter enclosed in bold-faced brackets [thus] in the above bill is not enacted and is intended to be omitted from the law.
Matter in bold-face type in the above bill is proposed language.
HCS HB 2474 2 (4) "Design-builder", any individual, partnership, joint venture, or corporation subject to a qualification-based selection that offers to provide or provides design services and general contracting services through a design-build contract or a progressive design-build contract in which services within the scope of the practice of professional architecture or engineering are performed respectively by a licensed architect or licensed engineer and in which services within the scope of general contracting are performed by a general contractor or other legal entity that furnishes architecture or engineering services and construction services either directly or through subcontracts or joint ventures;
(6) "Design criteria package", performance-oriented program, scope, and specifications for the design-build project sufficient to permit a design-builder to prepare a response to a political subdivision's request for proposals for a design-build project or a SCS HCS HB 2474 3 progressive design-build project, which may include capacity, durability, standards, ingress and egress requirements, performance requirements, description of the site, surveys, soil and environmental information concerning the site, interior space requirements, material quality standards, design and construction schedules, site development requirements, provisions for utilities, storm water retention and disposal, parking requirements, applicable governmental code requirements, preliminary designs for the project or portions thereof, and other criteria for the intended use of the project;
(6) "Design criteria package", performance-oriented program, scope, and specifications for the design-build project sufficient to permit a design-builder to prepare a response to a political subdivision's request for proposals for a design-build project or a progressive design-build project, which may include capacity, durability, standards, ingress and egress requirements, performance requirements, description of the site, surveys, soil and environmental information concerning the site, interior space requirements, material quality standards, design and construction schedules, site development requirements, provisions for utilities, storm water retention and disposal, parking requirements, applicable governmental code requirements, preliminary designs for the project or portions thereof, and other criteria for the intended use of the project;
(8) "Progressive design-build contract", a contract that is subject to a two-stage qualification-based selection process as described in subdivision (1) of subsection 13 of this section between a political subdivision and a design-builder to furnish the architectural, engineering, and related design services and the labor, materials, supplies, equipment, and other construction services required for a progressive design-build project;
(8) "Progressive design-build contract", a contract that is subject to a two-stage qualification-based selection process as described in subdivision (1) of subsection 13 of this section between a political subdivision and a design-builder to furnish the architectural, engineering, and related design services and the labor, materials, supplies, HCS HB 2474 3 equipment, and other construction services required for a progressive design-build project;
In using a design-build contract or a progressive design-build contract, the political subdivision shall determine the scope and level of detail required to permit qualified SCS HCS HB 2474 4 persons to submit proposals in accordance with the request for proposals given the nature of the project.
In using a design-build contract or a progressive design-build contract, the political subdivision shall determine the scope and level of detail required to permit qualified persons to submit proposals in accordance with the request for proposals given the nature of the project.
(1) No political subdivision using a progressive design-build contract under this section shall be required to include, as a condition of eligibility, the following:
A design criteria consultant [shall] may be employed or retained by the political subdivision to assist in preparation of the design criteria package and request for proposal, perform periodic site visits to observe adherence to the design criteria, prepare progress reports, review and approve progress and final pay applications of the design-builder, review shop drawings and submissions, provide input in disputes, help interpret the construction documents, perform inspections upon substantial and final completion, assist in warranty inspections, and provide any other professional service assisting with the project administration of a design-build project or a progressive design-build project.
evaluations, awards, or points based upon any requirement, certification, standard, or policy that is not directly related to the construction, safety, durability, permitting, or operation of the project.
(2) The provisions in subdivision (1) of this subsection shall include, but not be limited to:
(a) Green building certification or rating systems;
(b) Sustainable development goals, plans, or climate-related goals;
(c) Environmental, social, political, ideological, and governance standards, or similar nonpecuniary standards;
(d) Environmental justice, social justice, diversity, equity, or inclusion objectives;
and (e) Any preference for materials, designs, contractors, subcontractors, consultants, or vendors based on political, social, environmental, or ideological criteria rather than cost, quality, safety, durability, lawful permitting, or ability to perform the work.
4.
Nothing in subsection 3 of this section shall be construed to prohibit a political subdivision from requiring compliance with applicable federal law, state law, local building codes, health and safety standards, engineering standards, environmental permits, site remediation requirements, stormwater requirements, flood-control requirements, utility requirements, or other lawful project-specific requirements directly related to the construction, safety, durability, permitting, or ordinary operation of the project.
[3.] 5.
A design criteria consultant shall be employed or retained by the political subdivision to assist in preparation of the design criteria package and request for proposal, perform periodic site visits to observe adherence to the design criteria, prepare progress reports, review and approve progress and final pay applications of the design-builder, review shop drawings and submissions, provide input in disputes, help interpret the construction documents, perform inspections upon substantial and final completion, assist in warranty inspections, and provide any other professional service assisting with the project administration of a design-build project or a progressive design-build project.
SCS HCS HB 2474 5 [4.] 6.
4.
Notice of requests for proposals shall be advertised by publication in a newspaper of general circulation published in the county where the political subdivision is located once a week for two consecutive weeks prior to opening the proposals, or by a virtual notice procedure that notifies interested parties for at least twenty various purchases, design contracts, construction contracts, or other contracts each year for the political subdivision.
Notice of requests for proposals shall be advertised by publication in a newspaper of general circulation HCS HB 2474 4 published in the county where the political subdivision is located once a week for two consecutive weeks prior to opening the proposals, or by a virtual notice procedure that notifies interested parties for at least twenty various purchases, design contracts, construction contracts, or other contracts each year for the political subdivision.
[5.] 7.
5.
[6.] 8.
6.
Phase II shall be SCS HCS HB 2474 6 the solicitation of a technical proposal including conceptual design for the project.
Phase II shall be the solicitation of a technical proposal including conceptual design for the project.
[9.] (4) Phase I shall require all design-builders to submit a statement of qualification that shall include, but not be limited to:
HCS HB 2474 5 [9.] (4) Phase I shall require all design-builders to submit a statement of qualification that shall include, but not be limited to:
[(2)] (b) References of owners for whom design-build projects, construction projects, or design projects have been performed;
[(2)](b) References of owners for whom design-build projects, construction projects, or design projects have been performed;
Show all 73 changed rows (33 more)
Previous
Latest
[10.] 9.
[10.] 7.
[11.] 10.
[11.] 8.
[12.] 11.
[12.] 9.
[13.] 12.
[13.] 10.
SCS HCS HB 2474 7 (1) The political subdivision shall invite the top qualified design-builders to participate in phase II of the process;
(1) The political subdivision shall invite the top qualified design-builders to participate in phase II of the process;
(3) The ability of the design-builder to meet the schedule for completing a project as specified by the political subdivision may be considered as an element of evaluation in phase II;
HCS HB 2474 6 (3) The ability of the design-builder to meet the schedule for completing a project as specified by the political subdivision may be considered as an element of evaluation in phase II;
[14.] 13.
[14.] 11.
SCS HCS HB 2474 8 (5) If the political subdivision determines that it is not in the best interest of the political subdivision to proceed with the project pursuant to the proposal offered by the design-builder with the highest total number of points, the political subdivision shall reject all proposals.
(5) If the political subdivision determines that it is not in the best interest of the political subdivision to proceed with the project pursuant to the proposal offered by the design-builder with the highest total number of points, the political subdivision shall reject all proposals.
In this event, all qualified and responsive design-builders with lower point totals shall receive a stipend and the responsive design-builder with the highest total number of points shall receive an amount equal to two times the stipend.
In this event, all qualified and responsive design-builders with lower point totals shall receive a stipend and the responsive design-builder with the highest total number of HCS HB 2474 7 points shall receive an amount equal to two times the stipend.
[15.] 14.
[15.] 12.
15.
13.
and (h) Any other information that the political subdivision in its discretion chooses to supply including, but not limited to, surveys, soil reports, drawings of existing SCS HCS HB 2474 9 structures, environmental studies, photographs, references to public records, or affirmative action and minority business enterprise requirements consistent with state and federal law.
and (h) Any other information that the political subdivision in its discretion chooses to supply including, but not limited to, surveys, soil reports, drawings of existing structures, environmental studies, photographs, references to public records, or affirmative action and minority business enterprise requirements consistent with state and federal law.
Phase II shall be the solicitation and evaluation of proposals describing the design-builder's approach to design development, preconstruction services, and construction of the project.
Phase HCS HB 2474 8 II shall be the solicitation and evaluation of proposals describing the design-builder's approach to design development, preconstruction services, and construction of the project.
This process of short- listing shall narrow the number of qualified design-builders to not more than three but not less than two.
This process of short-listing shall narrow the number of qualified design-builders to not more than three but not less than two.
SCS HCS HB 2474 10 (6) The political subdivision shall have discretion to disqualify any design- builder who, in the political subdivision's opinion, lacks the minimum qualifications required to perform the work.
(6) The political subdivision shall have discretion to disqualify any design- builder who, in the political subdivision's opinion, lacks the minimum qualifications required to perform the work.
(8) Phase II of the process shall be conducted as follows:
HCS HB 2474 9 (8) Phase II of the process shall be conducted as follows:
Any innovations, or risk-management strategies proposed for the project;
Any innovations, sustainability measures, or risk-management strategies proposed for the project;
(d) Evaluation of phase II proposals shall be qualifications-based.
(d) Evaluation of Phase II proposals shall be qualifications-based.
(e) The political subdivision shall rank the phase II proposals according to the criteria and weighting established in the request for proposals and may conduct interviews as part of the evaluation;
(e) The political subdivision shall rank the Phase II proposals according to the criteria and weighting established in the request for proposals and may conduct interviews as part of the evaluation;
and (g) During the preconstruction phase, the design-builder and the political subdivision shall collaborate to advance the design to a level sufficient to establish a fixed contract amount or guaranteed maximum price, consistent with agreed-upon SCS HCS HB 2474 11 milestones and deliverables.
and (g) During the preconstruction phase, the design-builder and the political subdivision shall collaborate to advance the design to a level sufficient to establish a fixed contract amount or guaranteed maximum price, consistent with agreed-upon milestones and deliverables.
(9) The provisions of this subsection shall expire on August 28, 2036.
[16.] 14.
16.
(1) As used in this subsection, "wastewater or water contract" means any design-build contract or progressive design-build contract that involves the provision of engineering and construction services either directly by a party to the contract or through HCS HB 2474 10 subcontractors retained by a party to the contract for a wastewater or water storage, conveyance, or treatment facility project.
(1) As used in this subsection, "wastewater or water contract" means any design- build contract or progressive design-build contract that involves the provision of engineering and construction services either directly by a party to the contract or through subcontractors retained by a party to the contract for a wastewater or water storage, conveyance, or treatment facility project.
(2) Any political subdivision may enter into a wastewater or water contract for design-build of a wastewater or water project.
(2) Any political subdivision may enter into a wastewater or water contract for design-build or progressive design-build of a wastewater or water project.
(5) A political subdivision planning a wastewater or water design-build project or progressive design-build project shall retain an engineer duly licensed in this state to assist in preparing any necessary documents and specifications and evaluations of design-build or progressive design-build proposals.
(5) A political subdivision planning a wastewater or water design-build project or progressive design-build project shall retain an engineer duly licensed in this state to assist in preparing any necessary documents and specifications and evaluations of design-build proposals.
17.
[17.] 15.
The payment bond requirements of section 107.170 shall apply to [the] design- build [project] projects and progressive design-build projects.
The payment bond requirements of section 107.170 shall apply to [the] design-build [project] projects and progressive design-build projects.
18.
[18.] 16.
19.
[19.] 17.
20.
[20.] 18.
Under section 327.465, any design-builder that enters into a design-build contract or progressive design-build contract with a political subdivision is exempt from the requirement that such person or entity hold a license or that such corporation hold a certificate SCS HCS HB 2474 12 of authority if the architectural, engineering, or land-surveying services to be performed under the design-build contract are performed through subcontracts or joint ventures with properly licensed or authorized persons or entities, and not performed by the design-builder or its own employees.
Under section 327.465, any design-builder that enters into a design-build contract or progressive design-build contract with a political subdivision is exempt from the requirement that such person or entity hold a license or that such corporation hold a certificate of authority if the architectural, engineering, or land-surveying services to be performed under the design-build contract are performed through subcontracts or joint ventures with properly licensed or authorized persons or entities, and not performed by the design-builder or its own employees.
21.
[21.] 19.
(1) Any metropolitan sewer district established under Article VI, Section 30(a) of the Constitution of Missouri;
HCS HB 2474 11 (1) Any metropolitan sewer district established under Article VI, Section 30(a) of the Constitution of Missouri;
View plain text versions (5)

Amendments

3 amendments

Click Show changes on an amendment above to see how it modifies the bill.

Action History

  1. Delivered to Governor

  2. Signed by President Pro Tem (S)

  3. Signed by House Speaker (H)

  4. House Message (H)

  5. Truly Agreed To and Finally Passed - AYES: 136 NOES: 5 PRESENT: 1

  6. House Adopts (H) - SCS, as amended

  7. Taken Up

  8. Reported Do Pass (H) - AYES: 6 NOES: 2 PRESENT: 0

  9. Voted Do Pass (H)

  10. Executive Session Completed (H)

  11. Referred: Fiscal Review(H)

  12. Reported to the House with... (H) - SCS, as amended

  13. Third Read and Passed with Amendments (S) - SA 1, SA 2, SA 4, adopted - AYES: 27 NOES: 0 PRESENT: 0

  14. SCS Adopted (S)

  15. Motion to Reconsider Adopted (S) - adoption of the SCS, as amended - AYES: 29 NOES: 0 PRESENT: 0

  16. Taken Up

  17. Placed on Informal Calendar - SCS, as amended, pending for Third Reading

  18. SCS Adopted (S) - SA 1, SA 2, adopted

  19. Taken Up for Third Reading (S)

  20. Placed on Informal Calendar

  21. Reported Do Pass (S)

  22. Voted Do Pass (S)

  23. Executive Session Held (S)

  24. Referred: Fiscal Oversight(S)

  25. SCS Reported Do Pass (S)

  26. SCS Voted Do Pass (S)

  27. Executive Session Held (S)

  28. Public Hearing Held (S)

  29. Public Hearing Scheduled (S) - Monday, April 27, 2026, 2:00 p.m., Senate Lounge - 3rd Floor

  30. Second read and referred: Local Government, Elections and Pensions(S)

  31. Reported to the Senate and First Read (S)

  32. Third Read and Passed (H) - AYES: 141 NOES: 5 PRESENT: 0

  33. Taken Up for Third Reading (H)

  34. Reported Do Pass (H) - AYES: 5 NOES: 0 PRESENT: 0

  35. Voted Do Pass (H)

  36. Executive Session Completed (H)

  37. Referred: Fiscal Review(H)

  38. Perfected (H)

  39. HCS Adopted (H)

  40. Title of Bill - Agreed To

  41. Taken Up for Perfection (H)

  42. Placed on the Informal Perfection Calendar (H)

  43. Reported Do Pass (H) - AYES: 11 NOES: 0 PRESENT: 0

  44. Voted Do Pass (H)

  45. Executive Session Completed (H)

  46. Referred: Rules - Administrative(H)

  47. HCS Reported Do Pass (H) - AYES: 15 NOES: 0 PRESENT: 0

  48. HCS Voted Do Pass (H)

  49. Executive Session Completed (H)

  50. Public Hearing Completed (H)

  51. Referred: Economic Development(H)

  52. Read Second Time (H)

  53. Read First Time (H)

  54. Prefiled (H)

Sponsors

Sponsorship breakdown

Export CSV (upgrade) →

1 sponsors · 0 co-sponsors · 198 not signed on

Sponsors (1)

Co-sponsors (0)

None.

Not signed on (198)

198 members have not signed on to this bill.

Show all 198 →

"Not signed on" means a member has not sponsored or co-sponsored this bill — it does not imply opposition. Members flagged Voted No have a recorded No vote on this bill.

Whip count is in markup. Polling the chamber and every recorded vote this session. Only the first open is slow. It’s instant for you after this. Calling the roll · Tallying · Engrossing

Votes

Subjects

Cross-referencing the record. Reading this bill against every other bill in the corpus by meaning, not keywords. Only the first open is slow. It’s instant for you after this. Matching · Ranking · Engrossing

Frequently asked questions

Who sponsors HB 2474?
HB 2474 is sponsored by John Voss (Republican).
What is the current status of HB 2474?
This bill has been enacted into law. Introduced December 17, 2025. Enacted.
Where can I track HB 2474?
Track HB 2474 free on One Click Politics — get push/email alerts when it moves.

Make your voice heard on HB 2474

Find the representatives who decide this bill and tell them where you stand — for yourself, or mobilize your whole list in one click with One Click Politics advocacy software.

Stay ahead of HB 2474

Last checked for changes about 1 month ago · updated continuously

One Click Politics tracks every bill in Congress and all 50 states.

Track this bill →