S 1526 — Construction Consensus Procurement Improvement Act of 2015
Last action — Placed on Senate Legislative Calendar under General Orders. Calendar No. 656.
Write to your legislator about it: a free email template →
No card. One bill, free forever — alerts when it moves.
-
✓Introduced
-
✓In Committee
-
Died in session
This bill died with 114th Congress. It reached “In Committee” and never advanced before the session ended, so it can no longer move — a new version would have to be reintroduced in the current session.
This bill is no longer active — its legislative session has ended, so there is no live prognosis. It would have to be reintroduced in the current session to move again.
Summary
Construction Consensus Procurement Improvement Act of 2015 (Sec. 3) This bill modifies the design-build selection procedures used by federal agencies soliciting offers to enter into civilian contracts for the design and construction of a public building, facility, or work. Two-phase selection procedures (i.e., submission of qualifications and then the submission of price and technical proposals in response to a request for proposal) must be used when a contracting officer determines that a project has a value of $750,000 or greater. But for contracts valued at less than $750,000, the contracting officer makes the same determination under current law as to whether the use of two-phase selection procedures is appropriate when the officer anticipates at least three offers for the contract. Federal agencies must report, each year through FY2021, on each instance where the agency awarded a design-build contract in which: (1) more than five finalists were selected for phase-two requests for proposals, or (2) the contract or order was awarded without using two-phase selection procedures. The Government Accountability Office must report on agency compliance with design-build contract procedures. (Sec. 4) The Federal Acquisition Regulatory Council must amend the Federal Acquisition Regulation to prohibit the use of reverse auctions as part of the two-phase selection procedure for awarding contracts for construction and design services. A "reverse auction," with respect to procurement by an agency, is: (1) a real-time auction conducted through an electronic medium among at least two offerors who compete by submitting bids for a supply or service contract with the ability to submit revised lower bids before the closing of the auction; and (2) the award of the contract, delivery order, task order, or purchase order to the offeror based on the price obtained through the auction process.
Bill Text
What changed in the latest version
305 added · 93 removedPlain-language change summary
The amendments to Bill S. 1526 make several changes, including the removal of sections related to payment protections for construction subcontractors and suppliers and adjustments to the surety bond guarantee program. The updated text also modifies clauses regarding contract values and the two-phase selection process for awarding contracts. These changes may affect how construction contracts are awarded and the payment protections available to subcontractors in government contracts.
1526 IntroducedReported in Senate (IS)](RS)] 114th<DOC> CONGRESSCalendar 1stNo. Session S.
1526656 To114th amendCONGRESS title2d 10Session andS. title 41, United States Code, to improve the manner in which Federal contracts for construction and design services are awarded, to prohibit the use of reverse auctions for design and construction services procurements, to amend title 31 and title 41, United States Code, to improve the payment protections available to construction contractors, subcontractors, and suppliers for work performed, and for other purposes.
1526 [Report No.
114-366] To amend title 10 and title 41, United States Code, to improve the manner in which Federal contracts for construction and design services are awarded, to prohibit the use of reverse auctions for design and construction services procurements, to amend title 31 and title 41, United States Code, to improve the payment protections available to construction contractors, subcontractors, and suppliers for work performed, and for other purposes.
Portman (for himselfhimself, and Ms.
Hirono)Hirono, introducedMs. the following bill;
whichAyotte, was read twice and referredMrs. to the Committee on Homeland Security and Governmental Affairs _______________________________________________________________________ A BILL To amend title 10 and title 41, United States Code, to improve the manner in which Federal contracts for construction and design services are awarded, to prohibit the use of reverse auctions for design and construction services procurements, to amend title 31 and title 41, United States Code, to improve the payment protections available to construction contractors, subcontractors, and suppliers for work performed, and for other purposes.
BeShaheen) itintroduced enacted by the Senatefollowing andbill; House of Representatives of the United States of America in Congress assembled, SECTION 1.
which was read twice and referred to the Committee on Homeland Security and Governmental Affairs October 27, 2016 Reported under authority of the order of the Senate of September 29, 2016, by Mr.
Johnson, with an amendment [Strike out all after the enacting clause and insert the part printed in italic] _______________________________________________________________________ A BILL To amend title 10 and title 41, United States Code, to improve the manner in which Federal contracts for construction and design services are awarded, to prohibit the use of reverse auctions for design and construction services procurements, to amend title 31 and title 41, United States Code, to improve the payment protections available to construction contractors, subcontractors, and suppliers for work performed, and for other purposes.
Be it enacted by the Senate and House of Representatives of the United States of America in Congress assembled, <DELETED>SECTION 1.
TABLE OF CONTENTS.</DELETED> <DELETED> (a) Short Title.--This Act may be cited as the ``Construction Consensus Procurement Improvement Act of 2015''.</DELETED> <DELETED> (b) Table of Contents.--The table of contents for this Act is as follows:</DELETED> <DELETED>Sec.
1.
Short title;
table of contents.
<DELETED>Sec.
2.
Congressional findings.
<DELETED>Sec.
3.
Design-build construction process improvement.
<DELETED>Sec.
4.
Prohibition on the use of a reverse auction for the award of a contract for design and construction services.
<DELETED>Sec.
5.
Assuring payment protections for construction subcontractors and suppliers under an alternative to a Miller Act payment bond.
<DELETED>Sec.
6.
SBA surety bond guarantee program.
<DELETED>SEC.
2.
CONGRESSIONAL FINDINGS.</DELETED> <DELETED> Congress makes the following findings:</DELETED> <DELETED> (1) The acquisition procedures that are often used effectively to procure products and other forms of services are not always appropriate for procurement of design and construction services.</DELETED> <DELETED> (2) Federal procurement officials often adopt contracting techniques from the private sector and have used those techniques effectively to procure products and services.</DELETED> <DELETED> (3) Design-build is a procurement technique Federal officials have adopted from the private sector that has worked well for procurement of design and construction services.</DELETED> <DELETED> (4) The current statutory framework for design- build could benefit from legislative refinement.</DELETED> <DELETED> (5) Reverse auctions are another procurement technique Federal officials have adopted from the private sector and used successfully to award contracts for the purchase of products that are commercially equivalent to commodities.</DELETED> <DELETED> (6) Despite their success in other contexts, reverse auctions are generally inappropriate for procurement of design and construction services, given the unique nature of each such project.</DELETED> <DELETED> (7) To ensure payment protection for contractors, subcontractors, and suppliers working on Federal construction projects, bonds backed by individual sureties must be placed in the care and custody of the Federal Government and be supported by assets that are real, sufficient, verifiable, and readily convertible into cash.</DELETED> <DELETED>SEC.
3.
DESIGN-BUILD CONSTRUCTION PROCESS IMPROVEMENT.</DELETED> <DELETED> (a) Civilian Contracts.--</DELETED> <DELETED> (1) In general.--Section 3309 of title 41, United States Code, is amended--</DELETED> <DELETED> (A) by amending subsection (b) to read as follows:</DELETED> <DELETED> ``(b) Criteria for Use.--</DELETED> <DELETED> ``(1) Contracts with a value of at least $750,000.--Two-phase selection procedures shall be used for entering into a contract for the design and construction of a public building, facility, or work when a contracting officer determines that the contract has a value of $750,000 or greater, as adjusted for inflation in accordance with section of this title.</DELETED> <DELETED> ``(2) Contracts with a value less than $750,000.-- For projects that a contracting officer determines have a value of less than $750,000, the contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when-- </DELETED> <DELETED> ``(A) the contracting officer anticipates that 3 or more offers will be received for the contract;</DELETED> <DELETED> ``(B) design work must be performed before an offeror can develop a price or cost proposal for the contract;</DELETED> <DELETED> ``(C) the offeror will incur a substantial amount of expense in preparing the offer;
and</DELETED> <DELETED> ``(D) the contracting officer has considered information such as--</DELETED> <DELETED> ``(i) the extent to which the project requirements have been adequately defined;</DELETED> <DELETED> ``(ii) the time constraints for delivery of the project;</DELETED> <DELETED> ``(iii) the capability and experience of potential contractors;</DELETED> <DELETED> ``(iv) the suitability of the project for use of the two-phase selection procedures;</DELETED> <DELETED> ``(v) the capability of the agency to manage the two-phase selection process;
and</DELETED> <DELETED> ``(vi) other criteria established by the agency.'';
and</DELETED> <DELETED> (B) in subsection (d), by striking ``The maximum number specified in the solicitation shall not exceed 5 unless the agency determines with respect to'' and all that follows through the period at the end and inserting the following:
``The maximum number specified in the solicitation shall not exceed 5 unless the head of the contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, approves the contracting officer's justification that an individual solicitation must have greater than 5 finalists to be in the Federal Government's interest.
The contracting officer shall provide written documentation of how a maximum number of offerors exceeding 5 is consistent with the purposes and objectives of the two-phase selection process.''.</DELETED> <DELETED> (2) Annual reports.--</DELETED> <DELETED> (A) In general.--Not later than November of 2016, 2017, 2018, 2019, and 2020, the head of each agency shall compile an annual report of each instance in which the agency awarded a design-build contract pursuant to section 3309 of title 41, United States Code, during the fiscal year ending in such calendar year, in which--</DELETED> <DELETED> (i) more than 5 finalists were selected for phase-two requests for proposals;
Show all 125 changed lines (85 more)
or</DELETED> <DELETED> (ii) the contract was awarded without using two-phase selection procedures.</DELETED> <DELETED> (B) Public availability.--The Director of the Office of Management and Budget shall facilitate public access to the reports, including by posting them on a publicly available Internet website.
A notice of the availability of each report shall be published in the Federal Register.</DELETED> <DELETED> (b) Defense Contracts.--</DELETED> <DELETED> (1) In general.--Section 2305a of title 10, United States Code, is amended--</DELETED> <DELETED> (A) by amending subsection (b) to read as follows:</DELETED> <DELETED> ``(b) Criteria for Use.--</DELETED> <DELETED> ``(1) Contracts with a value of at least $750,000.--Two-phase selection procedures shall be used for entering into a contract for the design and construction of a public building, facility, or work when a contracting officer determines that the contract has a value of $750,000 or greater, as adjusted for inflation in accordance with section of title 41, United States Code.</DELETED> <DELETED> ``(2) Contracts with a value less than $750,000.-- For projects that a contracting officer determines have a value of less than $750,000, the contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when-- </DELETED> <DELETED> ``(A) the contracting officer anticipates that 3 or more offers will be received for the contract;</DELETED> <DELETED> ``(B) design work must be performed before an offeror can develop a price or cost proposal for the contract;</DELETED> <DELETED> ``(C) the offeror will incur a substantial amount of expense in preparing the offer;
and</DELETED> <DELETED> ``(D) the contracting officer has considered information such as--</DELETED> <DELETED> ``(i) the extent to which the project requirements have been adequately defined;</DELETED> <DELETED> ``(ii) the time constraints for delivery of the project;</DELETED> <DELETED> ``(iii) the capability and experience of potential contractors;</DELETED> <DELETED> ``(iv) the suitability of the project for use of the two-phase selection procedures;</DELETED> <DELETED> ``(v) the capability of the agency to manage the two-phase selection process;
and</DELETED> <DELETED> ``(vi) other criteria established by the Department of Defense.'';
and</DELETED> <DELETED> (B) in subsection (d), by striking ``The maximum number specified in the solicitation shall not exceed 5 unless the agency determines with respect to'' and all that follows through the period at the end and inserting the following:
``The maximum number specified in the solicitation shall not exceed 5 unless the head of the contracting activity approves the contracting officer's justification that an individual solicitation must have greater than 5 finalists to be in the Federal Government's interest.
The contracting officer shall provide written documentation of how a maximum number of offerors exceeding 5 is consistent with the purposes and objectives of the two-phase selection process.''.</DELETED> <DELETED> (2) Annual reports.--</DELETED> <DELETED> (A) In general.--Not later than November of 2016, 2017, 2018, 2019, and 2020, the Secretary of Defense shall compile an annual report of each instance in which the Department awarded a design-build contract pursuant to section 2305a of title 10, United States Code, during the fiscal year ending in such calendar year, in which--</DELETED> <DELETED> (i) more than 5 finalists were selected for phase-two requests for proposals;
or</DELETED> <DELETED> (ii) the contract was awarded without using two-phase selection procedures.</DELETED> <DELETED> (B) Public availability.--The Director of the Office of Management and Budget shall facilitate public access to the reports, including by posting them on a publicly available Internet website.
A notice of the availability of each report shall be published in the Federal Register.</DELETED> <DELETED> (c) GAO Reports.--</DELETED> <DELETED> (1) Civilian contracts.--Not later than 270 days after the deadline for the final reports required under subsection (f) of section 3309 of title 41, United States Code, as added by subsection (a)(1), the Comptroller General of the United States shall issue a report analyzing the compliance of the various Federal agencies with the requirements of such section.</DELETED> <DELETED> (2) Defense contracts.--Not later than 270 days after the deadline for the final reports required under subsection (f) of section 2305a of title 10, United States Code, as added by subsection (b)(1), the Comptroller General of the United States shall issue a report analyzing the compliance of the Department of Defense with the requirements of such section.</DELETED> <DELETED>SEC.
4.
PROHIBITION ON THE USE OF A REVERSE AUCTION FOR THE AWARD OF A CONTRACT FOR DESIGN AND CONSTRUCTION SERVICES.</DELETED> <DELETED> (a) Prohibition.--Not later than 180 days after the date of the enactment of this Act, the Federal Acquisition Regulatory Council, in consultation with the Administrator for Federal Procurement Policy, shall amend the Federal Acquisition Regulation to prohibit the use of reverse auctions for awarding contracts for construction and design services.</DELETED> <DELETED> (b) Definitions.--For purposes of this section--</DELETED> <DELETED> (1) the term ``design and construction services'' means--</DELETED> <DELETED> (A) site planning and landscape design;</DELETED> <DELETED> (B) architectural and engineering services (including surveying and mapping defined in section of title 40, United States Code);</DELETED> <DELETED> (C) interior design;</DELETED> <DELETED> (D) performance of construction work for facility, infrastructure, and environmental restoration projects;</DELETED> <DELETED> (E) delivery and supply of construction materials to construction sites;
and</DELETED> <DELETED> (F) construction or substantial alteration or repair of public buildings or public works;
and</DELETED> <DELETED> (2) the term ``reverse auction'' means, with respect to procurement by an agency--</DELETED> <DELETED> (A) a real-time auction conducted through an electronic medium between a group of offerors who compete against each other by submitting bids for a contract or task order with the ability to submit revised bids throughout the course of the auction;
and</DELETED> <DELETED> (B) the award of the contract or task order to the offeror who submits the lowest bid.</DELETED> <DELETED>SEC.
5.
ASSURING PAYMENT PROTECTIONS FOR CONSTRUCTION SUBCONTRACTORS AND SUPPLIERS UNDER AN ALTERNATIVE TO A MILLER ACT PAYMENT BOND.</DELETED> <DELETED> Chapter 93 of subtitle VI of title 31, United States Code, is amended--</DELETED> <DELETED> (1) by adding at the end the following new section:</DELETED> <DELETED>``Sec.
9310.
Individual sureties</DELETED> <DELETED> ``If another applicable law or regulation permits the acceptance of a bond from a surety that is not subject to sections 9305 and 9306 and is based on a pledge of assets by the surety, the assets pledged by such surety shall--</DELETED> <DELETED> ``(1) consist of eligible obligations described under section 9303(a);
and</DELETED> <DELETED> ``(2) be submitted to the official of the Government required to approve or accept the bond, who shall deposit the assets with a depository described under section 9303(b).'';
and</DELETED> <DELETED> (2) in the table of sections for such chapter, by adding at the end the following new item:</DELETED> <DELETED>``9310.
Individual sureties.''.
<DELETED>SEC.
6.
SBA SURETY BOND GUARANTEE PROGRAM.</DELETED> <DELETED> Section 411(c)(1) of the Small Business Investment Act of (15 U.S.C.
694b(c)(1)) is amended by striking ``70'' and inserting ``90''.</DELETED> SECTION 1.
SHORT TITLE;
Sec.
5.
Assuring payment protections for construction subcontractors and suppliers under an alternative to a Miller Act payment bond.
Sec.
6.
SBA surety bond guarantee program.
(7) To ensure payment protection for contractors, subcontractors, and suppliers working on Federal construction projects, bonds backed by individual sureties must be placed in the care and custody of the Federal Government and be supported by assets that are real, sufficient, verifiable, and readily convertible into cash.
(a) Civilian Contracts.-- (1) In general.--Section 33093309(b) of title 41, United States Code, is amended--amended (A) by amending subsection (b) to read as follows:
``(b) Criteria for Use.-- ``(1) Contracts with a value of at least $750,000.--Two- phase selection procedures shall be used for entering into a contract for the design and construction of a public building, facility, or work when a contracting officer determines that the contractproject has a value of $750,000 or greater, as adjusted for inflation in accordance with section 1908 of this title.
and ``(vi) other criteria established by the agency.'';agency.''.
and(2) (B)Annual inreports.-- subsection(A) (d),In bygeneral.--Not strikinglater ``Thethan maximumNovember number30 specifiedof in2017, 2018, 2019, 2020, and 2021, the solicitationhead of each agency shall notcompile exceedan 5annual unlessreport of each instance in which the agency determinesawarded witha respectdesign-build to''contract andpursuant allto thatsection follows3309 throughof thetitle period41, atUnited States Code, during the endfiscal andyear insertingending thein following:such calendar year, in which-- (i) more than 5 finalists were selected for phase-two requests for proposals;
``Theor maximum(ii) number specified in the solicitationcontract shallor notorder exceedwas 5awarded unlesswithout theusing headtwo-phase ofselection theprocedures. contracting activity, delegable to a level no lower than the senior contracting official within the contracting activity, approves the contracting officer's justification that an individual solicitation must have greater than 5 finalists to be in the Federal Government's interest.
The contracting officer shall provide written documentation of how a maximum number of offerors exceeding 5 is consistent with the purposes and objectives of the two-phase selection process.''.
(2) Annual reports.-- (A) In general.--Not later than November 30 of 2016, 2017, 2018, 2019, and 2020, the head of each agency shall compile an annual report of each instance in which the agency awarded a design-build contract pursuant to section 3309 of title 41, United States Code, during the fiscal year ending in such calendar year, in which-- (i) more than 5 finalists were selected for phase-two requests for proposals;
or (ii) the contract was awarded without using two-phase selection procedures.
(b) DefenseGAO Contracts.--Reports.--Not (1)later Inthan general.--Section270 2305adays after the deadline for the final reports required under subsection (f) of section 3309 of title 10,41, United States Code, isas amended--added (A) by amending subsection (b)(a)(1), tothe readComptroller asGeneral follows:of the United States shall issue a report analyzing the compliance of the various Federal agencies with the requirements of such section.
``(b) Criteria for Use.-- ``(1) Contracts with a value of at least $750,000.--Two- phase selection procedures shall be used for entering into a contract for the design and construction of a public building, facility, or work when a contracting officer determines that the contract has a value of $750,000 or greater, as adjusted for inflation in accordance with section 1908 of title 41, United States Code.
``(2) Contracts with a value less than $750,000.--For projects that a contracting officer determines have a value of less than $750,000, the contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when-- ``(A) the contracting officer anticipates that 3 or more offers will be received for the contract;
``(B) design work must be performed before an offeror can develop a price or cost proposal for the contract;
``(C) the offeror will incur a substantial amount of expense in preparing the offer;
and ``(D) the contracting officer has considered information such as-- ``(i) the extent to which the project requirements have been adequately defined;
``(ii) the time constraints for delivery of the project;
``(iii) the capability and experience of potential contractors;
``(iv) the suitability of the project for use of the two-phase selection procedures;
``(v) the capability of the agency to manage the two-phase selection process;
and ``(vi) other criteria established by the Department of Defense.'';
and (B) in subsection (d), by striking ``The maximum number specified in the solicitation shall not exceed 5 unless the agency determines with respect to'' and all that follows through the period at the end and inserting the following:
``The maximum number specified in the solicitation shall not exceed 5 unless the head of the contracting activity approves the contracting officer's justification that an individual solicitation must have greater than 5 finalists to be in the Federal Government's interest.
The contracting officer shall provide written documentation of how a maximum number of offerors exceeding 5 is consistent with the purposes and objectives of the two-phase selection process.''.
(2) Annual reports.-- (A) In general.--Not later than November 30 of 2016, 2017, 2018, 2019, and 2020, the Secretary of Defense shall compile an annual report of each instance in which the Department awarded a design-build contract pursuant to section 2305a of title 10, United States Code, during the fiscal year ending in such calendar year, in which-- (i) more than 5 finalists were selected for phase-two requests for proposals;
or (ii) the contract was awarded without using two-phase selection procedures.
(B) Public availability.--The Director of the Office of Management and Budget shall facilitate public access to the reports, including by posting them on a publicly available Internet website.
A notice of the availability of each report shall be published in the Federal Register.
(c) GAO Reports.-- (1) Civilian contracts.--Not later than 270 days after the deadline for the final reports required under subsection (f) of section 3309 of title 41, United States Code, as added by subsection (a)(1), the Comptroller General of the United States shall issue a report analyzing the compliance of the various Federal agencies with the requirements of such section.
(2) Defense contracts.--Not later than 270 days after the deadline for the final reports required under subsection (f) of section 2305a of title 10, United States Code, as added by subsection (b)(1), the Comptroller General of the United States shall issue a report analyzing the compliance of the Department of Defense with the requirements of such section.
(a) Prohibition.--NotFinding.--Congress laterfinds thanthat, 180in dayscontrast afterto thea datetraditional ofauction the enactment of this Act, the Federal Acquisition Regulatory Council, in consultationwhich with the Administratorbuyers forbid Federalup Procurement Policy, shall amend the Federalprice, Acquisitionsellers Regulationbid todown prohibit the useprice ofin a reverse auctionsauction. for awarding contracts for construction and design services.
(b) Definitions.--ForProhibition.--Not purposeslater than 180 days after the date of the enactment of this section--Act, (1)the Federal Acquisition Regulatory Council, in consultation with the termAdministrator ``designfor andFederal constructionProcurement services''Policy, means--shall (A)amend sitethe planningFederal Acquisition Regulation to prohibit the use of reverse auctions as part of the two-phase selection procedure for awarding contracts for construction and landscapedesign design;services.
(c) Definitions.--For purposes of this section-- (1) the term ``design and construction services'' means-- (A) site planning and landscape design;
(D) performance of substantial construction work for facility, infrastructure, and environmental restoration projects;
andor (F) construction or substantial alteration or repair of public buildings or public works;
and (2) the term ``reverse auction'' means, with respect to procurement by an agency-- (A) a real-time auction conducted through an electronic medium betweenamong a2 groupor ofmore offerors who compete against each other by submitting bids for a contractsupply or taskservice ordercontract with the ability to submit revised lower bids throughoutat any time before the courseclosing of the auction;
and (B) the award of the contractcontract, ordelivery order, task order, or purchase order to the offerorofferor, whoin submitswhole or in part, based on the lowestprice bid.obtained through the auction process.
SEC.Calendar No.
5.656 114th CONGRESS 2d Session S.
ASSURING1526 PAYMENT[Report PROTECTIONSNo. FOR CONSTRUCTION SUBCONTRACTORS AND SUPPLIERS UNDER AN ALTERNATIVE TO A MILLER ACT PAYMENT BOND.
Chapter114-366] 93_______________________________________________________________________ ofA subtitleBILL VITo ofamend title 31,10 and title 41, United States Code, isto amended--improve (1)the bymanner addingin atwhich Federal contracts for construction and design services are awarded, to prohibit the enduse of reverse auctions for design and construction services procurements, to amend title 31 and title 41, United States Code, to improve the followingpayment newprotections section:available to construction contractors, subcontractors, and suppliers for work performed, and for other purposes.
``Sec._______________________________________________________________________ October 27, 2016 Reported with an amendment
9310.
Individual sureties ``If another applicable law or regulation permits the acceptance of a bond from a surety that is not subject to sections 9305 and 9306 and is based on a pledge of assets by the surety, the assets pledged by such surety shall-- ``(1) consist of eligible obligations described under section 9303(a);
and ``(2) be submitted to the official of the Government required to approve or accept the bond, who shall deposit the assets with a depository described under section 9303(b).'';
and (2) in the table of sections for such chapter, by adding at the end the following new item:
``9310.
Individual sureties.''.
SEC.
6.
SBA SURETY BOND GUARANTEE PROGRAM.
Section 411(c)(1) of the Small Business Investment Act of 1958 (15 U.S.C.
694b(c)(1)) is amended by striking ``70'' and inserting ``90''.
<all>
Show all 125 changed rows (85 more)
View plain text versions (2)
- Reported Reported to Senate Current html October 27, 2016
- Introduced Introduced in Senate html June 08, 2015
Sections of law this bill changes
3 sections in 3 lawsFrom the bill's own amending language, matched to the official United States Code (current through Public Law 119-142).
Repealed] · 10 U.S.C. ch. 137 1 section
-
§ 2305a Renumbered § 3241] Amends
10 U.S.C. § 2305a
This section is renumbered in the current Code.
5 other bills also change this section · Follow it → Official text at uscode.house.gov ↗
Small business investment program · 15 U.S.C. ch. 14B 1 section
-
§ 694b Surety bond guarantees Amends
15 U.S.C. § 694b — at 694b(c)(1)
The law today
(a) Authority of Administration to guarantee surety against loss from principal’s breach of bond (1) (A) The Administration may, upon such terms and conditions as it may prescribe, guarantee and enter into commitments to guarantee any surety against loss resulting from a breach of the terms of a bid bond, payment bond, performance bond, or bonds ancillary thereto, by a principal on any total work order or contract amount at the time of bond execution that does not exceed $6,500,000, as adjusted for inflation in accordance with section 1908 of title 41. (B) The Administrator may guarantee a surety under subparagraph (A) for a total work order or contract amount that does not exceed $10,000,000, if a contracting officer of a Federal agency certifies that such a guarantee is necessary. (2) The terms and conditions of said guarantees and commitments may vary from surety to surety on the basis of the Administration’s experience with the particular surety. (3) The Administration may authorize any surety, without further administration approval, to issue, monitor, and service such bonds subject to the Administration’s guarantee. (4) No such guarantee may be issued, unless— (A) the person who would be principal under the bond is a small business concern; (B) the bond is required in order for such person to bid on a contract, or to serve as a prime contractor or subcontractor thereon; (C) such person is not able to obtain such bond on reasonable terms and conditions without a guarantee under this section; and (D) there is a reasonable expectation that such principal will perform the covenants and conditions of the contract with respect to which such bond is required, and the terms and conditions of such bond are reasonable in the light of the risks involved and the extent of the surety’s participation. (5) (A) The Administration shall promptly act upon an application from a surety to participate in the Preferred Surety Bond Guarantee Program, authorized by paragraph (3), in accordance with criteria and procedures established in regulations pursuant to subsection (d). (B) The Administration is authorized to reduce the allotment of bond guarantee authority or terminate the participation of a surety in the Preferred Surety Bond Guarantee Program based on the rate of participation of such surety during the 4 most recent fiscal year quarters compared to the median rate of participation by the other sureties in the program. (b) Indemnification of surety against loss from avoiding breach Subject to the provisions of this section, in connection with the issuance by the Administration of a guarantee to a surety as provided by subsection (a), the Administration may agree to indemnify such surety against a loss sustained by such surety in avoiding or attempting to avoid a breach of the terms of a bond guaranteed by the Administration pursuant to subsection (a): Provided, however— (1) prior to making any payment under this subsection, the Administration shall first determine that a breach of the terms of such bond was imminent; (2) a surety must obtain approval from the Administration prior to making any payments pursuant to this subsection unless the surety is participating under the authority of subsection (a)(3); and (3) no payment by the Administration pursuant to this subsection shall exceed 10 per centum of the contract price unless the Administrator determines that a greater payment should be made as a result of a finding by the Administrator that the surety’s loss sustained in avoiding or attempting to avoid such breach was necessary and reasonable. In no event shall the Administration pay a surety pursuant to this subsection an amount exceeding the guaranteed share of the bond available to such surety pursuant to subsection (a). (c) Limitation of liability Any guarantee or agreement to indemnify under this section shall obligate the Administration to pay to the surety a sum— (1) not to exceed 90 per centum of the loss incurred and paid...26 other bills also change this section · Follow it → Official text at uscode.house.gov ↗
Planning and solicitation · 41 U.S.C. ch. 33 1 section
-
§ 3309 Design-build selection procedures Amends
41 U.S.C. § 3309 — at 3309(b)
The law today
(a) Authorization.— Unless the traditional acquisition approach of design-bid-build established under sections 1101 to 1104 of title 40 or another acquisition procedure authorized by law is used, the head of an executive agency shall use the two-phase selection procedures authorized in this section for entering into a contract for the design and construction of a public building, facility, or work when a determination is made under subsection (b) that the procedures are appropriate for use. (b) Criteria for Use.— A contracting officer shall make a determination whether two-phase selection procedures are appropriate for use for entering into a contract for the design and construction of a public building, facility, or work when— (1) the contracting officer anticipates that 3 or more offers will be received for the contract; (2) design work must be performed before an offeror can develop a price or cost proposal for the contract; (3) the offeror will incur a substantial amount of expense in preparing the offer; and (4) the contracting officer has considered information such as the following: (A) The extent to which the project requirements have been adequately defined. (B) The time constraints for delivery of the project. (C) The capability and experience of potential contractors. (D) The suitability of the project for use of the two-phase selection procedures. (E) The capability of the agency to manage the two-phase selection process. (F) Other criteria established by the agency. (c) Procedures Described.— Two-phase selection procedures consist of the following: (1) Development of scope of work statement.— The agency develops, either in-house or by contract, a scope of work statement for inclusion in the solicitation that defines the project and provides prospective offerors with sufficient information regarding the Federal Government’s requirements (which may include criteria and preliminary design, budget parameters, and schedule or delivery requirements) to enable the offerors to submit proposals that meet the Federal Government’s needs. If the agency contracts for development of the scope of work statement, the agency shall contract for architectural and engineering services as defined by and in accordance with sections 1101 to 1104 of title 40. (2) Solicitation of phase-one proposals.— The contracting officer solicits phase-one proposals that— (A) include information on the offeror’s— (i) technical approach; and (ii) technical qualifications; and (B) do not include— (i) detailed design information; or (ii) cost or price information. (3) Evaluation factors.— The evaluation factors to be used in evaluating phase-one proposals are stated in the solicitation and include specialized experience and technical competence, capability to perform, past performance of the offeror’s team (including the architect-engineer and construction members of the team), and other appropriate factors, except that cost-related or price-related evaluation factors are not permitted. Each solicitation establishes the relative importance assigned to the evaluation factors and subfactors that must be considered in the evaluation of phase-one proposals. The agency evaluates phase-one proposals on the basis of the phase-one evaluation factors set forth in the solicitation. (4) Selection by contracting officer.— (A) Number of offerors selected and what is to be evaluated.— The contracting officer selects as the most highly qualified the number of offerors specified in the solicitation to provide the property or services under the contract and requests the selected offerors to submit phase-two competitive proposals that include technical proposals and cost or price information. Each solicitation establishes with respect to phase two— (i) the technical submission for the proposal, including design concepts or proposed solutions to requirements addressed within the scope of work, or both; and (ii) the evaluation factors and subfactors, including cost or pr...8 other bills also change this section · Follow it → Official text at uscode.house.gov ↗
Also cites: 40 U.S.C. § 1101, 41 U.S.C. § 1908
Action History
-
Placed on Senate Legislative Calendar under General Orders. Calendar No. 656.
-
Committee on Homeland Security and Governmental Affairs. Reported by Senator Johnson under authority of the order of the Senate of 09/29/2016 with an amendment in the nature of a substitute. With written report No. 114-366.
-
Committee on Homeland Security and Governmental Affairs. Ordered to be reported with an amendment in the nature of a substitute favorably.
-
Read twice and referred to the Committee on Homeland Security and Governmental Affairs.
Sponsors
- Rob Portman · Primary
Sponsorship breakdown
Export CSV (upgrade) →1 sponsors · 0 co-sponsors · 547 not signed on
Sponsors (1)
Co-sponsors (0)
None.
Not signed on (547)
547 members have not signed on to this bill.
Show all 547 →"Not signed on" means a member has not sponsored or co-sponsored this bill — it does not imply opposition. Members flagged Voted No have a recorded No vote on this bill.
Frequently asked questions
- What does S 1526 do?
- Construction Consensus Procurement Improvement Act of 2015 (Sec. 3) This bill modifies the design-build selection procedures used by federal agencies soliciting offers to enter into civilian contracts for the design and construction of a public building, facility, or work. Two-phase selection procedures (i.e., submission of qualifications and then the submission of price and technical proposals in response to a request for proposal) must be used when a contracting officer determines that a project has a value of $750,000 or greater. But for contracts valued at less than $750,000, the contracting officer makes the same determination under current law as to whether the use of two-phase selection procedures is appropriate when the officer anticipates at least three offers for the contract. Federal agencies must report, each year through FY2021, on each instance where the agency awarded a design-build contract in which: (1) more than five finalists were selected for phase-two requests for proposals, or (2) the contract or order was awarded without using two-phase selection procedures. The Government Accountability Office must report on agency compliance with design-build contract procedures. (Sec. 4) The Federal Acquisition Regulatory Council must amend the Federal Acquisition Regulation to prohibit the use of reverse auctions as part of the two-phase selection procedure for awarding contracts for construction and design services. A "reverse auction," with respect to procurement by an agency, is: (1) a real-time auction conducted through an electronic medium among at least two offerors who compete by submitting bids for a supply or service contract with the ability to submit revised lower bids before the closing of the auction; and (2) the award of the contract, delivery order, task order, or purchase order to the offeror based on the price obtained through the auction process.
- Who sponsors S 1526?
- S 1526 is sponsored by Rob Portman (R).
- What is the current status of S 1526?
- This bill died with 114th Congress. It reached “In Committee” and never advanced before the session ended, so it can no longer move — a new version would have to be reintroduced in the current session.
- Where can I track S 1526?
- Track S 1526 free on One Click Politics — get push/email alerts when it moves.
Make your voice heard on S 1526
Find the representatives who decide this bill and tell them where you stand — for yourself, or mobilize your whole list in one click with One Click Politics advocacy software.
Stay ahead of S 1526
Last checked for changes 16 days ago · updated continuously
One Click Politics tracks every bill in Congress and all 50 states.
Track this bill →