Texas 89th Legislature, Regular Session Status: Enacted Bipartisan · sponsors 8 R · 3 D

SB 6 — Relating to the planning for, interconnection and operation of, and costs related to providing service for certain electrical loads and to the generation of electric power by a water supply or sewer service corporation.

Last action — Effective immediately

Write to your legislator about it: a free email template →

No card. One bill, free forever — alerts when it moves.

  1. ✓
    Introduced
  2. ✓
    In Committee
  3. ✓
    Passed Senate
  4. ✓
    Passed House
  5. ✓
    To Executive
  6. 6
    Enacted

This bill has been enacted into law. Introduced February 12, 2025. Enacted.

Signed by Governor Greg Abbott (Republican) on June 20, 2025.

Summary

Relating to electricity planning and infrastructure costs for large loads.

In the bill's own words, from its opening clause.

Bill Text

What changed in the latest version

358 added · 270 removed

Plain-language change summary

The amended bill includes new text specifying that large load customers, including those requesting significant interconnections, must contribute to the costs of connecting to electric utilities. It also clarifies that electric cooperatives or municipally owned utilities that do not have customer choice must pass these interconnection costs to large load customers based on their determinations. The changes emphasize planning for and the operational aspects of connecting large electrical loads, which may impact how new businesses interact with energy providers in Texas.

→
Previous
Latest
By:AAKing, et al.
S.B.ANo.A6 AN ACT relating to the planning for, interconnection and operation of, and costs related to providing service for certain electrical loads and to the generation of electric power by a water supply or sewer service corporation.
S.B.ANo.A6 AAAAA A BILL TO BE ENTITLED AN ACT relating to electricity planning and infrastructure costs for large loads.
(c-1) AAThe commission by rule shall ensure that a large load customer who is subject to the standards adopted under Section 37.0561 contributes to the recovery of the interconnecting electric utility’s costs to interconnect the large load to the utility’ s system.
(c-1)AAThe commission by rule shall ensure that a large load customer who is subject to the standards adopted under Section 37.0561 contributes to the recovery of the interconnecting electric utility’s costs to interconnect the large load to the utility’ s system.
(c-2)AAAn electric cooperative or municipally owned utility that has not adopted customer choice shall pass through to a large load customer who is subject to the standards adopted under Section 37.0561 the reasonable costs to interconnect the large load in a manner determined by the electric cooperative or municipally owned utility.
(c-2) AAAn electric cooperative or municipally owned utility that has not adopted customer choice shall pass through to a large load customer who is subject to the standards adopted under Section 37.0561 the reasonable costs to interconnect the large load in a manner determined by the electric cooperative or municipally owned utility.
SECTIONA2.AASubchapter B, Chapter 37, Utilities Code, is amended by adding Section 37.0561 to read as follows:
SECTION A2.AASubchapter B, Chapter 37, Utilities Code, is amended by adding Section 37.0561 to read as follows:
A37.0561.AAPLANNING REQUIREMENTS FOR LARGE LOADS.
A37.0561.AAPLANNING FOR AND INTERCONNECTION OF LARGE LOADS.
(a) The commission by rule shall establish standards for interconnecting large load customers in the ERCOT power region in a manner designed to support business development in this state while minimizing the potential for stranded infrastructure costs and S.B.ANo.A6 maintaining system reliability.
(a) For the purposes of this section, a large load customer includes an entity requesting an interconnection that exceeds the S.B.ANo.A6 demand threshold adopted under Subsection (c) and a successor in interest to such an entity.
(b) AAThe standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region.
(b) AAThe commission by rule shall establish standards for interconnecting large load customers in the ERCOT power region in a manner designed to support business development in this state while minimizing the potential for stranded infrastructure costs and maintaining system reliability.
The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (a).
(c)AAThe standards must apply only to customers requesting a new or expanded interconnection where the total load at a single site would exceed a demand threshold established by the commission based on the size of loads that significantly impact transmission needs in the ERCOT power region.
(c)AAThe standards must require each large load customer subject to Subsection (b) to disclose to the interconnecting electric utility or municipally owned utility whether the customer is pursuing a substantially similar request for electric service, inside or outside this state, the approval of which would result in the customer materially changing, delaying, or withdrawing the interconnection request.
The commission shall establish a demand threshold of 75 megawatts unless the commission determines that a lower threshold is necessary to accomplish the purposes described by Subsection (b).
(d) AAThe standards must require each large load customer subject to Subsection (c) to disclose to the interconnecting electric utility or municipally owned utility whether the customer is pursuing a substantially similar request for electric service in this state the approval of which would result in the customer materially changing, delaying, or withdrawing the interconnection request.
The commission by rule shall prohibit an electric utility or municipally owned utility from selling, sharing, or disclosing information submitted to the utility under this subsection other than a disclosure to the commission or the independent organization certified under Section 39.151 for the ERCOT power region, subject to appropriate confidentiality protections.
The commission by rule shall prohibit an electric utility or municipally owned utility from selling, sharing, or disclosing information submitted to the utility under this subsection other than a disclosure to the commission or the independent organization certified under Section 39.151 for the S.B.ANo.A6 ERCOT power region, subject to appropriate confidentiality protections.
(d)AAThe standards must require each interconnected large load customer subject to Subsection (b) to disclose to the interconnecting electric utility or municipally owned utility information about the customer’s on-site backup generating S.B.ANo.A6 facilities and require the interconnecting electric utility or municipally owned utility to provide the information to the independent organization certified under Section 39.151 for the ERCOT power region.
(e) AAThe standards must require each interconnected large load customer subject to Subsection (c) to disclose to the interconnecting electric utility or municipally owned utility information about the customer’s on-site backup generating facilities and require the interconnecting electric utility or municipally owned utility to provide the information to the independent organization certified under Section 39.151 for the ERCOT power region.
The independent organization certified under Section 39.151 for the ERCOT power region shall establish a threshold during an energy emergency alert where the organization may, after reasonable notice, direct the applicable electric utility or municipally owned utility to require the large load customer to either deploy the customer’s on-site backup generating facility or curtail load.
The independent organization shall establish a threshold before or during an energy emergency alert at which the organization may issue reasonable notice that large load customers with on-site backup generating facilities may be directed to either deploy the customer’s on-site backup generating facilities or curtail load.
The independent organization certified under Section 39.151 for the ERCOT power region shall include a deployment under this section as firm load shed when calculating any price adjustments for reliability deployments.
After the independent organization deploys all available market services, except for frequency responsive services, the independent organization may direct the applicable electric utility or municipally owned utility to require the large load customer to either deploy the customer ’s on-site backup generating facilities or curtail load.
The independent organization shall include a deployment under this section as firm load shed when calculating any price adjustments for reliability deployments.
(1)AAauthorize or require a violation of any emissions limitation in state or federal law or a violation of any other environmental regulation;
S.B.ANo.A6 (1)AAauthorize or require a violation of any emissions limitation in state or federal law or a violation of any other environmental regulation;
(e) AAThe standards must set a flat study fee of at least $100,000 to be paid to the interconnecting electric utility or municipally owned utility for initial transmission screening studies for large loads subject to Subsection (b).
(f)AAThe standards must set a flat study fee of at least $100,000 to be paid to the interconnecting electric utility or municipally owned utility for initial transmission screening studies for large loads subject to Subsection (c).
A large load customer that requests additional capacity following the screening S.B.ANo.A6 study must pay an additional study fee based on the new request.
A large load customer that requests additional capacity following the screening study must pay an additional study fee based on the new request.
(f)AAThe standards must include a method for a large load customer subject to Subsection (b) to demonstrate site control for the proposed load location through an ownership interest, lease, or another legal interest acceptable to the commission.
(g)AAThe standards must include a method for a large load customer subject to Subsection (c) to demonstrate site control for the proposed load location through an ownership interest, lease, or another legal interest acceptable to the commission.
(g) AAThe standards must include uniform financial commitment standards for the development of transmission infrastructure needed to serve a large load customer subject to Subsection (b) before an electric utility or municipally owned utility may submit a project for review to the independent organization certified under Section 39.151 for the ERCOT power region based on the large load customer’ s demand.
(h)AAThe standards must include uniform financial commitment requirements for the development of transmission infrastructure needed to serve a large load customer subject to Subsection (c).
(2)AAcontribution in aid of construction;
S.B.ANo.A6 (2)AAcontribution in aid of construction;
S.B.ANo.A6 (h)AASecurity provided under Subsection (g)(1) must be refunded, in whole or in part, after the security is applied to any outstanding amounts owed:
(i)AASecurity provided under Subsection (h)(1) must be refunded, in whole or in part, after the security is applied to any outstanding amounts owed:
or (2)AAif the large load customer withdraws the customer s request for all or a portion of the requested capacity.
(2)AAif the large load customer withdraws the customer s request for all or a portion of the requested capacity;
(i) AAThe standards must establish a procedure to allow the independent organization certified under Section 39.151 for the ERCOT power region to access any information collected by the interconnecting electric utility or municipally owned utility to ensure compliance with the standards for transmission planning analysis.
or (3)AAif capacity subject to a financial commitment will be reallocated to one or more other customers.
Any customer-specific or competitively sensitive information obtained under this subsection is confidential and not subject to disclosure under Chapter 552, Government Code.
(j)AAThe commission shall establish uniform requirements for determining when capacity that is subject to an outstanding financial commitment under this section may be reallocated.
(j)AAThe commission may not limit the authority of a municipally owned utility or an electric cooperative to impose retail electric service requirements for large load customers on their systems in addition to the standards adopted under this section.
(k) AAThe standards must establish a procedure to allow the independent organization certified under Section 39.151 for the ERCOT power region to access any information collected by the interconnecting electric utility or municipally owned utility to ensure compliance with the standards for transmission planning analysis.
(k)AANotwithstanding the forecasted load growth and additional load currently seeking interconnection required to be considered under Section 37.056(c-1), the commission by rule shall establish criteria by which the independent organization certified under Section 39.151 for the ERCOT power region includes forecasted large load of any peak demand in the organization ’s transmission S.B.ANo.A6 planning and resource adequacy models and reports.
Any customer-specific or competitively sensitive S.B.ANo.A6 information obtained under this subsection is confidential and not subject to disclosure under Chapter 552, Government Code.
SECTION A3.AASection 39.002, Utilities Code, is amended to read as follows:
(l) AAThe commission may not limit the authority of a municipally owned utility or an electric cooperative to impose electric service requirements for large load customers on their systems in addition to the standards adopted under this section.
(m)AANotwithstanding the forecasted load growth and additional load currently seeking interconnection required to be considered under Section 37.056(c-1), the commission by rule shall establish criteria by which the independent organization certified under Section 39.151 for the ERCOT power region includes forecasted large load of any peak demand in the organization ’ s transmission planning and resource adequacy models and reports.
SECTIONA3.AASection 39.002, Utilities Code, is amended to read as follows:
SECTIONA4.AASubchapter D, Chapter 39, Utilities Code, is amended by adding Sections 39.169 and 39.170 to read as follows:
SECTION A4.AASubchapter D, Chapter 39, Utilities Code, is amended by adding Sections 39.169 and 39.170 to read as follows:
S.B.ANo.A6 Sec.A39.169.AACO-LOCATION OF LARGE LOAD CUSTOMER WITH EXISTING GENERATION RESOURCE.
(a) A power generation company, municipally owned utility, or electric cooperative must submit a notice to the independent organization certified under Section 39.151 for the ERCOT power region before implementing a net metering arrangement between an operating facility registered with the independent organization as a stand-alone generation resource as of September 1, 2025, and a new large load customer as described by Section 37.0561(c).
(b)AAThis section does not apply to a generation resource:
(1)AAthe registration for which included a co-located large load customer at the time of energization, regardless of whether the load was energized at a later date;
or (2)AAa majority interest of which is owned indirectly or directly as of January 1, 2025, by a parent company of the customer that participates in the new net metering arrangement.
(c) AAThe electric cooperative, transmission and distribution utility, or municipally owned utility that provides electric service at the location of the new net metering arrangement may for reasonable cause including a violation of other law, object to the arrangement, provided however, that no reasonable cause objection may be raised after a final decision by the commission is issued under this section.
(d) AAThe independent organization certified under Section 39.151 for the ERCOT power region shall study the system impacts of a proposed net metering arrangement and removal of generation for which the independent organization receives a notice under S.B.ANo.A6 Subsection (a) after the independent organization receives all information regarding the arrangement required by the independent organization to be submitted to the independent organization.
The independent organization must complete the study and submit the results to the commission with any associated recommendations not later than the 120th day after the independent organization receives all required information regarding the arrangement.
Show all 95 changed rows (55 more)
Previous
Latest
Not later than the 60th day after the date the commission receives the study results from the independent organization, the commission shall approve, deny, or impose reasonable conditions on the proposed net metering arrangement as necessary to maintain system reliability, including transmission security and resource adequacy impacts.
The conditions must require a generation resource that makes dispatchable capacity available to the ERCOT power region before the implementation of a net metering arrangement under this section to make at least that amount of dispatchable capacity available to the ERCOT power region after the implementation of the arrangement at the direction of the independent organization in advance of an anticipated emergency condition.
The conditions may include:
(1)AArequiring the retail customer who is served behind-the-meter to reduce load during certain events;
(2)AArequiring the generation resource to make capacity available to the ERCOT power region during certain events;
or (3)AArequiring customers to be held harmless for stranded or underutilized transmission assets resulting from the behind-the-meter operation.
S.B.ANo.A6 (e)AAIf the commission does not approve, deny, or impose reasonable conditions on a proposed net metering arrangement before the expiration of the deadline established by Subsection (d), the commission is considered to have approved the arrangement.
(f)AAIf conditions imposed under Subsection (d) are not limited to a specific period, the commission shall review the conditions at least every five years to determine whether the conditions should be extended or rescinded.
(g)AAThe parties to a proceeding under this section are limited to the commission, the independent organization certified under Section 39.151 for the ERCOT power region, the interconnecting electric cooperative, transmission and distribution utility, or municipally owned utility, and a party in the net metering arrangement.
(h)AAThe commission shall post the decision made on each notice submitted under this section on the commission ’s Internet website.
The commission may not post information regarding the decision that is competitively sensitive or otherwise considered confidential.
A39.169.AACO-LOCATION OF RETAIL CUSTOMER WITH EXISTING GENERATION RESOURCE.
A39.170.AALARGE LOAD DEMAND MANAGEMENT SERVICE.
(a) A power generation company, municipally owned utility, or electric cooperative must submit a notice to the commission and the independent organization certified under Section 39.151 for the ERCOT power region before implementing a net metering arrangement between an existing, operating facility registered with the independent organization as a generation resource and a new large load customer as described by Section 37.0561(b).
(a)AAThe commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to ensure that each electric cooperative, transmission and distribution utility, and municipally owned utility serving a transmission-voltage customer develops a protocol, including the installation of any necessary equipment or technology before the customer is interconnected, to allow the load to be curtailed S.B.ANo.A6 during firm load shed.
(b) AAThe new net metering arrangement must be requested or consented to by the electric cooperative, electric utility, or municipally owned utility certificated to provide retail electric S.B.ANo.A6 service at the location.
The electric cooperative, transmission and distribution utility, or municipally owned utility shall confer with the customer to the extent feasible to shed load in a coordinated manner.
The electric cooperative, electric utility, or municipally owned utility may withhold consent to a proposal that is consistent with the determination provided under Subsection (c) and applicable law only for a reasonable cause.
(c)AAWith input from the independent organization certified under Section 39.151 for the ERCOT power region, not later than the 180th day after the date the commission receives the notice under Subsection (a), the commission shall approve, deny, or impose reasonable conditions on a proposed net metering arrangement described by Subsection (a) as necessary to maintain system reliability, including transmission security and resource adequacy impacts.
The conditions may:
(1)AArequire the retail customer who is served behind-the-meter to reduce load during certain events;
(2)AArequire the generation resource to make capacity available to the ERCOT power region during certain events;
or (3)AAprovide that the owner of the generation resource may be held liable for stranded or underutilized transmission assets resulting from the behind-the-meter operation.
(d)AAIf the commission does not approve, deny, or impose reasonable conditions on a proposed net metering arrangement before the expiration of the deadline established by Subsection (c), the commission is considered to have approved the arrangement.
(e) AAIf conditions imposed under Subsection (c) are not limited to a specific period, the commission shall review the conditions at least every five years to determine whether the conditions should be extended or rescinded.
S.B.ANo.A6 (f)AAThe parties to a proceeding under this section are limited to the commission, the independent organization certified under Section 39.151 for the ERCOT power region, the interconnecting electric cooperative, electric utility, or municipally owned utility, and a party in the net metering arrangement.
Sec.A39.170.AALARGE LOAD DEMAND MANAGEMENT SERVICE.
(a)AAThe commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to ensure that each electric cooperative, electric utility, and municipally owned utility serving a transmission-voltage customer develops a protocol and installs, or requires to be installed, before the customer is interconnected, any necessary equipment to allow the load to be curtailed during firm load shed.
The electric cooperative, electric utility, or municipally owned utility shall confer with the customer to the extent feasible to shed load in a coordinated manner.
(b) AAThe commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated S.B.ANo.A6 emergency condition.
(b) AAThe commission shall require the independent organization certified under Section 39.151 for the ERCOT power region to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 megawatts to be deployed in the event of an anticipated emergency condition.
(c)AAThe independent organization certified under Section 39.151 for the ERCOT power region shall include a deployment under this section when calculating any price adjustments for reliability deployments.
(c) AAThe independent organization certified under Section S.B.ANo.A6 39.151 for the ERCOT power region shall include a deployment under this section when calculating any price adjustments for reliability deployments.
SECTIONA5.AA(a) The Public Utility Commission of Texas shall evaluate whether the existing methodology used to charge wholesale transmission costs to distribution providers under Section 35.004(d), Utilities Code, continues to appropriately assign costs for transmission investment.
SECTION A5.AASubchapter A, Chapter 67, Water Code, is amended by adding Section 67.0115 to read as follows:
Sec.A67.0115.AAELECTRIC GENERATION.
(a) A corporation may generate electric power for use in the corporation ’ s operations, limited to:
(1)AApowering water well pumps, service pumps, and other equipment for the production, treatment, and transportation of raw water;
and (2)AApowering infrastructure for the treatment and delivery of potable drinking water.
(b)AAFor the purposes of Subsection (a), a corporation operating solely as a wholesale water supplier or sewer service in a county with a population of less than 350,000 may generate excess electric power in conjunction with the uses described in Subsection (a) for sale in the ERCOT power region to provide revenue for the corporation only if the corporation:
(1)AAprimarily generates electric power solely for the uses described in Subsection (a);
and (2)AAregisters as a power generation company under Section 39.351, Utilities Code.
(c) AAA corporation that generates electric power for sale under Subsection (b) shall account for and use the revenue from those sales in a manner that complies with Section 67.004.
The revenue that accrues from those sales of electric power may be used S.B.ANo.A6 by the corporation only for:
(1)AAthe corporation ’s costs of producing and selling electric power, including administration, employees, equipment, fuel, and maintenance;
or (2)AAa purpose described by Section 67.002.
SECTION A6.AA(a) The Public Utility Commission of Texas shall evaluate whether the existing methodology used to charge wholesale transmission costs to distribution providers under Section 35.004(d), Utilities Code, continues to appropriately assign costs for transmission investment.
(2)AAwhether alternative methods to calculate S.B.ANo.A6 wholesale transmission rates would more appropriately assign the cost of providing access to and wholesale service from the transmission system, such as consideration of multiple seasonal peak demands, demand during different length daily intervals, or peak energy intervals;
(2)AAwhether alternative methods to calculate wholesale transmission rates would more appropriately assign the cost of providing access to and wholesale service from the transmission system, such as consideration of multiple seasonal peak demands, demand during different length daily intervals, or peak energy intervals;
(b)AAThe Public Utility Commission of Texas shall evaluate whether the commission s retail ratemaking practices ensure that transmission cost recovery appropriately charges the system costs that are caused by each customer class.
(b) AAThe Public Utility Commission of Texas shall evaluate whether the commission s retail ratemaking practices ensure that S.B.ANo.A6 transmission cost recovery appropriately charges the system costs that are caused by each customer class.
(c)AAThe Public Utility Commission of Texas shall begin the evaluation required under Subsection (a) of this section not later than the 90th day after the effective date of this Act.
(c) AAThe Public Utility Commission of Texas shall begin the evaluation required under Subsection (a) of this section not later than the 90th day after the effective date of this Act.
SECTIONA6.AASection 35.004(c-1), Utilities Code, as added by this Act, applies only to an interconnection agreement entered into on or after the effective date of this Act.
SECTIONA7.AASection 35.004(c-1), Utilities Code, as added by this Act, applies only to an interconnection agreement entered into on or after the effective date of this Act.
SECTION A7.AAThis Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution.
SECTION A8.AAThis Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution.
If this Act does not receive the vote necessary for immediate effect, this S.B.ANo.A6 Act takes effect September 1, 2025.
If this Act does not receive the vote necessary for immediate effect, this Act takes effect September 1, 2025.
11
S.B.ANo.A6 ______________________________AAAA______________________________ President of the SenateAAAAAAAAAAAAASpeaker of the House I hereby certify that S.B.ANo.A6 passed the Senate on MarchA19,A2025, by the following vote:
YeasA31, NaysA0;
and that the Senate concurred in House amendments on May 29, 2025, by the following vote:
YeasA31, NaysA0.
______________________________ AAAASecretary of the Senate I hereby certify that S.B.ANo.A6 passed the House, with amendments, on May A27,A2025, by the following vote:
YeasA103, NaysA25, two present not voting.
______________________________ AAAAChief Clerk of the House Approved:
______________________________ AAAAAAAAAAAAADate ______________________________ AAAAAAAAAAAGovernor 14
View plain text versions (5)

Action History

  1. Effective immediately

  2. Signed by the Governor

  3. Sent to the Governor

  4. Signed in the House

  5. Signed in the Senate

  6. Co-author authorized

  7. Reported enrolled

  8. Senate concurs in House amendment(s)-reported

  9. Record vote

  10. Senate concurs in House amendment(s)

  11. Read

  12. House amendment(s) laid before the Senate

  13. House passage as amended reported

  14. Statement(s) of vote recorded in Journal

  15. Record vote

  16. Passed

  17. Read 3rd time

  18. Record vote

  19. Passed to 3rd reading as amended

  20. Statement of Leg. Intent Recorded in Journal

  21. Statement(s) of vote recorded in Journal

  22. Record vote

  23. Amended

  24. Record vote

  25. Amendment adopted as amended

  26. Statement(s) of vote recorded in Journal

  27. Record vote

  28. Amendment amended

  29. Amendment(s) offered

  30. Read 2nd time

  31. Placed on Major State Calendar

  32. Considered in Calendars

  33. Committee report sent to Calendars

  34. Committee report distributed

  35. Comte report filed with Committee Coordinator

  36. Reported favorably as substituted

  37. Committee substitute considered in committee

  38. Considered in formal meeting

  39. Recommitted to committee

  40. Point of order withdrawn

  41. Statement(s) of vote recorded in Journal

  42. Record vote

  43. Amended

  44. Statement(s) of vote recorded in Journal

  45. Record vote

  46. Amended

  47. Statement(s) of vote recorded in Journal

  48. Record vote

  49. Amendment adopted as amended

  50. Statement(s) of vote recorded in Journal

  51. Record vote

  52. Amendment amended

  53. Amendment(s) offered

  54. Read 2nd time

  55. Placed on General State Calendar

  56. Considered in Calendars

  57. Committee report sent to Calendars

  58. Committee report distributed

  59. Comte report filed with Committee Coordinator

  60. Reported favorably as substituted

  61. Committee substitute considered in committee

  62. Considered in formal meeting

  63. Left pending in committee

  64. Testimony taken/registration(s) recorded in committee

  65. Considered in public hearing

  66. Referred to State Affairs

  67. Read first time

  68. Received from the Senate

  69. Reported engrossed

  70. Record vote

  71. Passed

  72. Read 3rd time

  73. Record vote

  74. Three day rule suspended

  75. Vote recorded in Journal

  76. Passed to engrossment as amended

  77. Vote recorded in Journal

  78. Amended

  79. Amendment(s) offered

  80. Read 2nd time

  81. Rules suspended-Regular order of business

  82. Co-author authorized

  83. Placed on intent calendar

  84. Co-author authorized

  85. Committee report printed and distributed

  86. Reported favorably as substituted

  87. Vote taken in committee

  88. Considered in public hearing

  89. Co-author authorized

  90. Left pending in committee

  91. Testimony taken in committee

  92. Considered in public hearing

  93. Scheduled for public hearing on . . .

  94. Co-author authorized

  95. Referred to Business & Commerce

  96. Read first time

  97. Filed

  98. Received by the Secretary of the Senate

Sponsors

Sponsorship breakdown

Export CSV (upgrade) →

3 sponsors · 8 co-sponsors · 174 not signed on

Sponsors (3)

Co-sponsors (8)

Not signed on (174)

174 members have not signed on to this bill.

Show all 174 →

"Not signed on" means a member has not sponsored or co-sponsored this bill — it does not imply opposition. Members flagged Voted No have a recorded No vote on this bill.

Whip count is in markup. Polling the chamber and every recorded vote this session. Only the first open is slow. It’s instant for you after this. Calling the roll · Tallying · Engrossing

Committees

Cross-referencing the record. Reading this bill against every other bill in the corpus by meaning, not keywords. Only the first open is slow. It’s instant for you after this. Matching · Ranking · Engrossing

Frequently asked questions

What does SB 6 do?
Relating to electricity planning and infrastructure costs for large loads.
Who sponsors SB 6?
SB 6 is sponsored by Phil King (Republican), Charles Schwertner (Republican), Carol Alvarado (Democratic), César Blanco (Democratic), Donna Campbell (Republican), Sarah Eckhardt (Democratic), Brent Hagenbuch (Republican), Bryan Hughes (Republican), Mayes Middleton (Republican), and Brandon Creighton (Republican).
What is the current status of SB 6?
This bill has been enacted into law. Introduced February 12, 2025. Enacted.
Where can I track SB 6?
Track SB 6 free on One Click Politics — get push/email alerts when it moves.

Make your voice heard on SB 6

Find the representatives who decide this bill and tell them where you stand — for yourself, or mobilize your whole list in one click with One Click Politics advocacy software.

Stay ahead of SB 6

Last checked for changes 19 days ago · updated continuously

One Click Politics tracks every bill in Congress and all 50 states.

Track this bill →