2025-21050: South Sutter Water District; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense

Get alerted when the next rule lands

New rules open for comment on their own schedule. Pick how you want to hear about them — we email you when one appears.

Publishing to members? Embed a live rule tracker on your own site — the proposed rules in your area and the comment deadlines closing on them, updating themselves. Free, one line of HTML.

Create a free account & build one →

What this rule does

The South Sutter Water District has applied for a new license to continue operating the Camp Far West Hydroelectric Project, and the Federal Energy Regulatory Commission is evaluating the environmental impacts of this relicensing. The schedule for completing this assessment has been updated, with the draft assessment expected to be issued in February 2026 and comments from the public due by the end of March 2026.

Plain-language description generated by AI — not the agency’s official summary, which we have not captured for this rule. Read the official text →

The rule, in full

320 words as published, November 25, 2025. View the original →

Federal Register, Volume 90 Issue 225 (Tuesday, November 25, 2025) [Federal Register Volume 90, Number 225 (Tuesday, November 25, 2025)] [Notices] [Page 53296] From the Federal Register Online via the Government Publishing Office [www.gpo.gov] [FR Doc No: 2025-21050] ----------------------------------------------------------------------- DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project No. 2997-031] South Sutter Water District; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense On December 28, 2023, the South Sutter Water District (SSWD) filed an application for a new license to continue to operate and maintain the 6.8-megawatt Camp Far West Hydroelectric Project No. 2997 (Camp Far West Project). On November 25, 2024, Commission staff issued a notice of intent to prepare an environmental assessment (EA) to evaluate the effects of relicensing the Camp Far West Project. The notice included an anticipated schedule for issuing the EA in November 2025. Staff are still evaluating the effects of relicensing the Camp Far West Project. In order for staff to fully consider all the information filed by SSWD, the procedural schedule for completing the EA is being revised as follows. Further revisions to the schedule may be made as appropriate. ------------------------------------------------------------------------ Milestone Target date ------------------------------------------------------------------------ Commission issues EA...................... February 27, 2026. Commission on the EA...................... March 29, 2026.\1\ ------------------------------------------------------------------------ \1\ The Commission's Rules of Practice and Procedure provide that if a filing deadline falls on a Saturday, Sunday, holiday, or other day when the Commission is closed for business, the filing deadline does not end until the close of business on the next business day [18 CFR 385.2007(a)(2)(2025)]. Because the deadline for the 30-day comment period falls on a Sunday, the filing deadline will be extended until the close of business on Monday, March 30, 2026. Questions regarding this notice may be directed to Quinn Emmering at (202) 502-6382 or [email protected]. Dated: November 20, 2025. Debbie-Anne A. Reese, Secretary. [FR Doc. 2025-21050 Filed 11-24-25; 8:45 am] BILLING CODE 6717-01-P

Don't miss the comment window

One Click Politics alerts you on every deadline, hearing, and rule change.

See all rules with comments due soon →