British Columbia Assessment Authority Regulation

B.C. Reg. 258/2022: Amendments to the Railway and Pipeline Corporations Valuation Regulation

Made under the Assessment Act

How does this rule affect your organization? One Click reads it against your profile and tells you, on Canada Federal Legislative Tracking. See plans →

Get alerted when the next rule lands

New rules land on their own schedule. Pick how you want to hear about them — we email you when one appears.

Publishing to members? Embed a live rule tracker on your own site — the proposed rules in your area and the comment deadlines closing on them, updating themselves. Free, one line of HTML.

The rule, in full

559 words as published, December 06, 2022. View the original →

B.C. Reg. 258/2022, deposited December 1, 2022, under the ASSESSMENT ACT [section 21]. Regulation of the British Columbia Assessment Authority, dated November 30, 2022. The British Columbia Assessment Authority orders that the Railway and Pipeline Corporations Valuation Regulation, B.C. Reg. 203/86, is amended as set out in the attached Appendix. — K. WITTENBERG, Chair, Board of Directors.

Appendix

1 Section 1 of the Railway and Pipeline Corporations Valuation Regulation, B.C. Reg. 203/86, is amended by striking out "2022" and substituting "2023". 2 Section 3 (2) (a) to (k) is repealed and the following substituted: (a) Class 1 track, $237 200 per kilometre; (b) Class 2 track, $231 600 per kilometre; (c) Class 3 track, $218 400 per kilometre; (d) Class 4 track, $157 600 per kilometre; (e) Class 5 track, $15 500 per kilometre; (f) Class 6 track, $121 300 per kilometre; (g) Class 7 track, $0 per kilometre; (h) Class 8 track, $190 400 per kilometre; (i) Class 9 track, $181 200 per kilometre; (j) Class 10 track, $151 200 per kilometre; (k) Class 11 track, $127 700 per kilometre. 3 Schedules A and B are repealed and the following Schedules A and B are substituted:

Schedule A

Outside Diameter of Pipe (mm) | Rate per Kilometre ($) Under 76 | 38 700 76 or more and under 88 | 42 800 88 or more and under 114 | 47 200 114 or more and under 141 | 60 800 141 or more and under 168 | 75 200 168 or more and under 219 | 89 500 219 or more and under 273 | 114 600 273 or more and under 323 | 143 600 323 or more and under 355 | 166 700 355 or more and under 406 | 196 500 406 or more and under 457 | 248 400 457 or more and under 508 | 284 500 508 or more and under 558 | 334 800 558 or more and under 609 | 413 800 609 or more and under 660 | 449 600 660 or more and under 711 | 485 700 For pipelines with outside diameter equal to or more than 711 mm, use Schedule B

Schedule B

Outside Diameter of Pipe (mm) | Rate per Kilometre ($) 219 or more and under 273 | 146 700 273 or more and under 323 | 163 300 323 or more and under 355 | 215 100 355 or more and under 406 | 239 000 406 or more and under 457 | 355 200 457 or more and under 508 | 380 500 508 or more and under 558 | 443 400 558 or more and under 609 | 604 000 609 or more and under 660 | 639 900 660 or more and under 711 | 671 400 711 or more and under 762 | 713 700 762 or more and under 863 | 812 700 863 or more and under 914 | 866 400 914 or more and under 965 | 921 200 965 or more and under 1 016 | 992 100 1 016 or more and under 1 066 | 1 064 300 1 066 or more and under 1 219 | 1 135 600 1 219 and more | 1 333 100 For pipelines with outside diameter less than 219 mm, use Schedule A