Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B
Section 97.2
Leave in the procurement, selection context
Cite as Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B, s. 97.2 · current to November 11, 2026 · consolidated from December 11, 2025 · read from e-Laws on November 17, 2026
The text
(1) In an application under section 92, leave to construct, expand or reinforce an electricity transmission line or to make an interconnection shall not be granted to a person if,
(a) the IESO has commenced, been directed to commence, or announced a future procurement process for the development, construction, expansion or reinforcement of that line or for the making of that interconnection, and the procurement process has not yet been completed or otherwise terminated;
(b) the IESO has commenced, been directed to commence, or announced a future process to select a transmitter for the development, construction, expansion or reinforcement of that line or for the making of that interconnection, and the process has not yet been completed or otherwise terminated;
(c) the IESO has completed a procurement process for the development, construction, expansion or reinforcement of that line or for the making of that interconnection, and the person is someone other than the person with whom the IESO has entered into a procurement contract respecting the development, construction, expansion, reinforcement or interconnection; or
(d) the IESO has completed a process to select a transmitter for the development, construction, expansion or reinforcement of that line or for the making of that interconnection, and the person is someone other than the selected transmitter. 2016, c. 10, Sched. 2, s. 16.
(2) If the applicant in an application under section 92 is a person with whom the IESO has entered into a procurement contract respecting the development, construction, expansion, reinforcement of the line or the making of the interconnection, the Board may make an order under section 96 without holding a hearing. 2016, c. 10, Sched. 2, s. 16.
(3) For the purposes of subsections (1) and (2),
“procurement contract” has the same meaning as in the Electricity Act, 1998. 2016, c. 10, Sched. 2, s. 16.
(4) Repealed: 2025, c. 22, Sched. 3, s. 11.
Read the Ontario Energy Board Act, 1998 on e-Laws ↗