Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B

Section 97

Condition, land-owner’s agreements

Cite as Ontario Energy Board Act, 1998, S.O. 1998, c. 15, Sched. B, s. 97 · current to November 11, 2026 · consolidated from December 11, 2025 · read from e-Laws on November 17, 2026

The text

In an application under section 90, 91 or 92, leave to construct shall not be granted until the applicant satisfies the Board that it has offered or will offer to each owner of land affected by the approved route or location an agreement in a form approved by the Board. 1998, c. 15, Sched. B, s. 97.
Read the Ontario Energy Board Act, 1998 on e-Laws ↗