(1) No cause of action arises against the Crown, any current or former member of the Executive Council, any current or former employee or agent of or adviser to the Crown, the Board, or any current or former member, employee or agent of the Board, as a direct or indirect result of,
(a) the enactment, operation or administration of any amendment to this Act by Schedule 2 to the Fixing the Hydro Mess Act, 2019;
(b) anything done or not done under the amendments to this Act by Schedule 2 to the Fixing the Hydro Mess Act, 2019; or
(c) anything related in any way to the involvement of the Government of Ontario in compensation matters, or other aspects of corporate governance, of the Board. 2019, c. 6, Sched. 2, s. 27.
(2) No proceeding, including but not limited to any proceeding for a remedy in contract, constructive dismissal, restitution, tort, misfeasance, bad faith, trust or fiduciary obligation, and any remedy under applicable securities laws or any other statute, that is directly or indirectly based on or related to anything referred to in subsection (1) may be brought or maintained against the Crown or against any person referred to in that subsection. 2019, c. 6, Sched. 2, s. 27.
(3) Subsection (2) applies to any action or other proceeding claiming any remedy or relief, including specific performance, injunction, declaratory relief, any form of compensation or damages, or any other remedy or relief, and includes a proceeding to enforce a judgment or order made by a court outside of Canada. 2019, c. 6, Sched. 2, s. 27.
(4) Subsections (2) and (3) apply regardless of whether the cause of action on which the proceeding is purportedly based arose before, on or after the day section 28 of Schedule 2 to the Fixing the Hydro Mess Act, 2019 came into force. 2019, c. 6, Sched. 2, s. 27.
(5) Any proceeding referred to in subsection (2) or (3) commenced before the day referred to in subsection (4) is deemed to have been dismissed, without costs, on that day. 2019, c. 6, Sched. 2, s. 27.
Read the Ontario Energy Board Act, 1998 on e-Laws ↗