The text
(1) The IESO shall, in accordance with the market rules, publish any amendment to the market rules at least 22 days before the amendment comes into force. 2004, c. 23, Sched. A, s. 42.
(2) The IESO shall give the Board a copy of the amendment and such other information as is prescribed by the regulations on or before the date the IESO publishes the amendment under subsection (1). 2004, c. 23, Sched. A, s. 42.
(3) Despite section 4.1 of the Statutory Powers Procedure Act and section 35.1 of this Act, the Board may, not later than 15 days after the amendment is published under subsection (1) and without holding a hearing, revoke the amendment on a date specified by the Board and refer the amendment back to the IESO for further consideration. 2004, c. 23, Sched. A, s. 42.
(4) Any person may apply to the Board for review of an amendment to the market rules by filing an application with the Board within 21 days after the amendment is published under subsection (1). 2004, c. 23, Sched. A, s. 42.
(5) Subsection 19 (4) of the Ontario Energy Board Act, 1998 applies to an application under subsection (4). 2004, c. 23, Sched. A, s. 42.
(6) The Board shall issue an order that embodies its final decision within 120 days after receiving an application for review of an amendment. 2004, c. 23, Sched. A, s. 42; 2017, c. 2, Sched. 10, s. 1.
(7) No application for review of an amendment under this section shall stay the operation of the amendment pending the completion of the Board’s review of the amendment unless the Board orders otherwise. 2004, c. 23, Sched. A, s. 42.
(8) In determining whether to stay the operation of an amendment, the Board shall consider,
(a) the public interest;
(b) the merits of the application;
(c) the possibility of irreparable harm to any person;
(d) the impact on consumers; and
(e) the balance of convenience. 2004, c. 23, Sched. A, s. 42.
(9) If, on completion of its review, the Board finds that the amendment is inconsistent with the purposes of this Act or unjustly discriminates against or in favour of a market participant or class of market participants, the Board shall make an order,
(a) revoking the amendment on a date specified by the Board; and
(b) referring the amendment back to the IESO for further consideration. 2004, c. 23, Sched. A, s. 42.