APPROVAL EXEMPTIONS, O. Reg. 525/98
Section 3.1
Storm water management works, construction activities
Cite as APPROVAL EXEMPTIONS, O. Reg. 525/98, s. 3.1 · current to November 11, 2026 · consolidated from September 1, 2026 · read from e-Laws on November 16, 2026
The text
Subsections 53 (1) and (3) of the Act do not apply to the use, operation, establishment, alteration, extension or replacement of or a change in a temporary storm water management works that is,
(a) used, operated, altered or extended only for the purpose of erosion and sediment control during construction activities;
(b) removed or decommissioned within 90 days after the construction activity ends; and
(c) located at a site that is not directly associated with mines, mine development, mine reclamation, pits or quarries. O. Reg. 250/26, s. 3.
3.2, 3.3 Revoked: O. Reg. 214/22, s. 2.
Read the APPROVAL EXEMPTIONS on e-Laws ↗
Made under Ontario Water Resources Act, R.S.O. 1990, c. O.40.