EDUCATION DEVELOPMENT CHARGES — GENERAL, O. Reg. 20/98
Section 2
Cite as EDUCATION DEVELOPMENT CHARGES — GENERAL, O. Reg. 20/98, s. 2 · current to November 11, 2026 · consolidated from April 11, 2022 · read from e-Laws on November 16, 2026
The text
(1) Costs that are attributable to excess land of a site are prescribed, for the purposes of paragraph 2 of subsection 257.53 (3) of the Act, as costs that are not education land costs. O. Reg. 20/98, s. 2 (1).
(2) Subsection (1) does not apply to costs described in paragraph 5 of subsection 257.53 (2) of the Act. O. Reg. 20/98, s. 2 (2).
(3) Land is not excess land if it is reasonably necessary,
(a) to meet a legal requirement relating to the site; or
(b) to allow the facilities for pupil accommodation that the board intends to provide on the site to be located there and to provide access to those facilities. O. Reg. 20/98, s. 2 (3).
(4) This section does not apply to land,
(a) that has already been acquired by the board before February 1, 1998; or
(b) in respect of which there is an agreement, entered into before February 1, 1998, under which the board is required to, or has an option to, purchase the land. O. Reg. 20/98, s. 2 (4).
(5) In this section,
“excess land” means the part of a school site that exceeds the maximum area determined, under Table 1 or Table 2 to this section, based on the number of pupils that can be accommodated in the school to be built on the site.
Table 1 Elementary Schools
Item | Column 1 Number of pupils | Column 2 Maximum area (acres)
1. | 1 to 400 | 4
2. | 401 to 500 | 5
3. | 501 to 600 | 6
4. | 601 to 700 | 7
5. | 701 or more | 8
Table 2 Secondary Schools
Item | Column 1 Number of pupils | Column 2 Maximum area (acres)
1. | 1 to 1000 | 12
2. | 1001 to 1100 | 13
3. | 1101 to 1200 | 14
4. | 1201 to 1300 | 15
5. | 1301 to 1400 | 16
6. | 1401 to 1500 | 17
7. | 1501 or more | 18