Development Charges Act, 1997, S.O. 1997, c. 27

Section 26

When development charge is payable

Cite as Development Charges Act, 1997, S.O. 1997, c. 27, s. 26 · current to November 11, 2026 · consolidated from June 2, 2026 · read from e-Laws on November 17, 2026

The text

(1) A development charge is payable for a development upon a building permit being issued for the development unless the development charge by-law provides otherwise under subsection (2). 1997, c. 27, s. 26 (1). (1.1) If a development consists of one building that requires more than one building permit, the development charge for the development is payable upon the first building permit being issued. 2015, c. 26, s. 6. (1.2) If a development consists of two or more phases that will not be constructed concurrently and are anticipated to be completed in different years, each phase of the development is deemed to be a separate development for the purposes of this section. 2015, c. 26, s. 6. (2) A municipality may, in a development charge by-law, provide that a development charge for services set out in paragraphs 1, 2, 3, 4 or 5 of subsection 2 (4) for development that requires approval of a plan of subdivision under section 51 of the Planning Act or a consent under section 53 of the Planning Act and for which a subdivision agreement or consent agreement is entered into, be payable immediately upon the parties entering into the agreement. 1997, c. 27, s. 26 (2); 2019, c. 9, Sched. 3, s. 7. (3) This section does not apply in cases where there is an agreement under section 27. 1997, c. 27, s. 26 (3).
Read the Development Charges Act, 1997 on e-Laws ↗