Environmental Bill of Rights, 1993, S.O. 1993, c. 28
Section 91
Discontinuance, abandonment, settlement, etc.
Cite as Environmental Bill of Rights, 1993, S.O. 1993, c. 28, s. 91 · current to November 11, 2026 · consolidated from February 22, 2024 · read from e-Laws on November 17, 2026
The text
(1) An action under section 84 may be discontinued or abandoned only with the approval of the court, on the terms that the court considers appropriate. 1993, c. 28, s. 91 (1).
(2) A settlement of an action under section 84 is not binding unless approved by the court. 1993, c. 28, s. 91 (2).
(3) A settlement of an action under section 84 that is approved by the court binds all past, present and future residents of Ontario. 1993, c. 28, s. 91 (3).
(4) In considering whether to dismiss an action under section 84 without a finding as to whether the plaintiff was entitled to judgment, whether for delay, for public interest reasons or for any other reason, or in considering whether to approve a discontinuance, abandonment or settlement of the action, the court shall consider whether notice should be given under section 88. 1993, c. 28, s. 91 (4).
Read the Environmental Bill of Rights, 1993 on e-Laws ↗