CONSTRUCTION PROJECTS, O. Reg. 213/91
Section 92
Cite as CONSTRUCTION PROJECTS, O. Reg. 213/91, s. 92 · current to November 11, 2026 · consolidated from April 20, 2026 · read from e-Laws on November 16, 2026
The text
(1) Design drawings by an engineer for the formwork, falsework or re-shoring,
(a) if a manufactured system is used, shall identify the components;
(b) if non-manufactured system components are used, shall show the size, grade and specifications of the non-manufactured system components;
(c) shall show the design loads for the structure and shall detail the bracing and external ties required to adequately support the design loads;
(d) if the structure is a unitized modular formwork or falsework structure intended to be lifted or moved as a unit, shall show the attachment points for rigging and hoisting; and
(e) shall set out the erection instructions that are specified by the manufacturer or by the engineer.
(f) Revoked: O. Reg. 85/04, s. 11.
(2) The constructor shall keep the design drawings on the project while the formwork, falsework or re-shoring is in use. O. Reg. 213/91, s. 92 (2).
Read the CONSTRUCTION PROJECTS on e-Laws ↗
Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.