CONSTRUCTION PROJECTS, O. Reg. 213/91
Section 233
Cite as CONSTRUCTION PROJECTS, O. Reg. 213/91, s. 233 · current to November 11, 2026 · consolidated from April 20, 2026 · read from e-Laws on November 16, 2026
The text
(1) A level area extending at least one metre from the upper edge of each wall of an excavation shall be kept clear of equipment, excavated soil, rock and construction material. O. Reg. 213/91, s. 233 (1).
(2) The stability of a wall of an excavation shall be maintained where it may be affected by stockpiling excavated soil or rock or construction materials. O. Reg. 213/91, s. 233 (2).
(3) No person shall operate a vehicle or other machine and no vehicle or other machine shall be located in such a way as to affect the stability of a wall of an excavation. O. Reg. 213/91, s. 233 (3).
(4) If a person could fall into an excavation that is more than 2.4 metres deep, a barrier at least 1.1 metres high shall be provided at the top of every wall of the excavation that is not sloped as described in clauses 234 (2) (e), (f) and (g). O. Reg. 213/91, s. 233 (4).
Read the CONSTRUCTION PROJECTS on e-Laws ↗
Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.