CONSTRUCTION PROJECTS, O. Reg. 213/91

Section 130

Cite as CONSTRUCTION PROJECTS, O. Reg. 213/91, s. 130 · current to November 11, 2026 · consolidated from April 20, 2026 · read from e-Laws on November 16, 2026

The text

(1) A scaffold shall be designed by an engineer and shall be erected in accordance with the design if the scaffold exceeds, (a) fifteen metres in height above its base support; or (b) ten metres in height above its base support if the scaffold is constructed of a tube and clamp system. O. Reg. 213/91, s. 130 (1); O. Reg. 375/22, s. 5. (2) Design drawings for a scaffold shall set out erection instructions and the rated loads for the scaffold. O. Reg. 85/04, s. 12. (3) An engineer or a competent worker designated by the supervisor of the project shall inspect the scaffold before it is used to ensure that it is erected in accordance with the design drawings. O. Reg. 213/91, s. 130 (3); O. Reg. 375/22, s. 5. (4) The person carrying out an inspection shall state in writing whether the scaffold is erected in accordance with the design drawings. O. Reg. 213/91, s. 130 (4). (5) The constructor shall keep at a project the design drawings and the written statement for a scaffold while the scaffold is erected. O. Reg. 213/91, s. 130 (5).
Read the CONSTRUCTION PROJECTS on e-Laws ↗

Made under Occupational Health and Safety Act, R.S.O. 1990, c. O.1.