Mining Act, R.S.O. 1990, c. M.14
Section 143.1
Specified changes by order
Cite as Mining Act, R.S.O. 1990, c. M.14, s. 143.1 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) The Minister may at any time, by order, require changes to a filed closure plan. 2023, c. 6, s. 11 (1).
(2) If a change ordered under subsection (1) is to a closure plan for a mine hazard under subsection 147 (1) and the order requires that a new schedule for completing the rehabilitation of the mine hazard be submitted, the following rules apply:
1. The person affected by the order shall submit the new schedule immediately.
2. The portion of the order that requires the submission of a new schedule for completing the rehabilitation of the mine hazard shall not be,
i. referred to an independent third party under subsection (3), or
ii. appealed under clause 152 (1) (b). 2019, c. 14, Sched. 7, s. 7; 2023, c. 6, s. 11 (2, 3).
(3) Subject to paragraph 2 of subsection (2), if changes are required under subsection (1), in addition to appealing any of them to the Tribunal under clause 152 (1) (b), the proponent may, within 30 days after receiving the order requiring changes, notify the Minister of the desire to have any of them that are not appealed to the Tribunal referred for a decision to an independent third party agreed upon by the proponent and the Minister. 2019, c. 14, Sched. 7, s. 7; 2023, c. 6, s. 11 (4), 28 (1).
(4) If the proponent and the Minister are unable to agree on an independent third party within 45 days after the Minister receives the notice of referral under subsection (3), the proponent who wishes to dispute the changes may appeal to the Tribunal any of the changes that the proponent desired to have referred, despite the 30 day period provided for appeal in subsection 152 (2), within 75 days after sending the notice of referral, failing which the changes that are not appealed shall be deemed to be accepted by the proponent. 2019, c. 14, Sched. 7, s. 7; 2023, c. 6, s. 28 (1).
(5) All costs incurred by an independent third party in connection with any work performed pursuant to a referral shall be borne by the proponent. 2019, c. 14, Sched. 7, s. 7.
(6) The decision of an independent third party is final and binds the proponent and the Minister, and an amendment to the closure plan shall be deemed to have been filed accordingly. 2019, c. 14, Sched. 7, s. 7; 2023, c. 6, s. 28 (1).
Read the Mining Act on e-Laws ↗