The text
(1) In imposing terms and conditions in an environmental compliance approval, the Director may include terms and conditions in respect of, but not limited to,
(a) future specified alterations, extensions, enlargements or replacements, including future specified alterations, extensions, enlargements or replacements to be carried out by persons prescribed by the regulations;
(b) operational parameters, including maximum rates of production, process limits, performance limits and parameters relating to equipment and infrastructure; and
(c) alterations, extensions, enlargements or replacements to be carried out within the operational parameters mentioned in clause (b), including alterations, extensions, enlargements or replacements to be carried out within the operational parameters by persons prescribed by the regulations. 2010, c. 16, Sched. 7, s. 2 (15).
(2) If the Director imposes terms and conditions mentioned in clause (1) (a), (b) or (c) in respect of alterations, extensions, enlargements or replacements to be carried out by persons prescribed by the regulations, the environmental compliance approval shall be deemed to include a condition that the holder of the approval must give the persons notice of the terms and conditions in the approval. 2010, c. 16, Sched. 7, s. 2 (15).
(3) Subsections 15.1.2 (2), 17.27 (2) and 17.30 (2) of the Environmental Assessment Act does not prohibit a Director from imposing terms and conditions mentioned in clause (1) (a), (b) or (c) in an environmental compliance approval, but the other applicable provisions of that Act continue to apply to any future alterations, extensions, enlargements or replacements that the Director may approve in an approval. 2010, c. 16, Sched. 7, s. 2 (15); 2020, c. 18, Sched. 6, s. 52 (1, 2).
(4) An environmental compliance approval is subject to any terms and conditions prescribed by the regulations. 2010, c. 16, Sched. 7, s. 2 (15).
(5) The Director may, in an environmental compliance approval in respect of any plant, structure, equipment, apparatus, mechanism, thing, waste management system, waste disposal site or sewage works that was established before the day this section comes into force, impose terms and conditions in respect of any associated structure, equipment, apparatus, mechanism, thing or works. 2010, c. 16, Sched. 7, s. 2 (15).