Environmental Assessment Act, R.S.O. 1990, c. E.18
Section 17.28.1
Definitions
Cite as Environmental Assessment Act, R.S.O. 1990, c. E.18, s. 17.28.1 · current to November 11, 2026 · consolidated from June 5, 2025 · read from e-Laws on November 17, 2026
The text
(1) In this section,
“designated activities” means the activities that are designated by Ontario Regulation 50/24 (Part II.3 Projects – Designations and Exemptions) made under the Act as a project to which Part II.3 applies; (“activités désignées”)
“waste disposal site activities” means the activities designated under section 2 of Ontario Regulation 284/24 (Designation – Chatham-Kent Waste Disposal Site) made under the Act as it read immediately before it was revoked. (“activités au lieu d’élimination des déchets”) 2025, c. 4, Sched. 3, s. 2 (1).
(2) Any waste disposal site activities that are designated activities are exempt from Part II.3. 2025, c. 4, Sched. 3, s. 2 (1).
Part II.4 Streamlined Environmental Assessments
Prohibition
17.29 (1) No person shall proceed with a Part II.4 project until the person has satisfied the prescribed requirements for commencing the project, including the completion of a prescribed environmental assessment process. 2020, c. 18, Sched. 6, s. 30.
Exception
(2) Despite subsection (1), a proponent of a Part II.4 project may apply under subsection 17.2 (1) to the Minister for approval to proceed with the Part II.4 project as a Part II.3 project. On and after the day the proponent applies under subsection 17.2 (1), the project shall be deemed to be a Part II.3 project and Part II.3 applies in respect of it instead of this section. 2020, c. 18, Sched. 6, s. 30.
Same
(3) Subsection (2) ceases to apply if the application for approval to proceed with a project as a Part II.3 project is withdrawn by the proponent. 2020, c. 18, Sched. 6, s. 30.
Same
(4) Despite subsection (1), if the Minister makes an order under subsection 17.31 (1) declaring the Part II.4 project to be a Part II.3 project for the purposes of this Act, this section ceases to apply with respect to the project and Part II.3 applies. 2020, c. 18, Sched. 6, s. 30.
Proceeding with project
(5) After the prescribed requirements for commencing a Part II.4 project have been satisfied, a person may proceed with the project but shall do so only in accordance with the prescribed requirements for proceeding with the project. 2020, c. 18, Sched. 6, s. 30.
Activities permitted before proceeding
17.30 (1) Before the proponent of a Part II.4 project has satisfied the prescribed requirements for commencing the project, a person may,
(a) take any action in connection with the project that may be necessary to comply with this Act;
(b) acquire property or rights in property in connection with the project;
(c) prepare a feasibility study and engage in research in connection with the project; or
(d) establish a reserve fund or another financing mechanism in connection with the project. 2020, c. 18, Sched. 6, s. 30.
Restriction on issuing certain documents
(2) No person shall issue a document evidencing that an authorization required at law to proceed with the project has been given until the proponent has satisfied the prescribed requirements for commencing the project. 2020, c. 18, Sched. 6, s. 30.
Exception
(3) Despite subsection (2), a document described in that subsection may be issued with respect to an activity permitted by subsection (1) before the proponent has satisfied the prescribed requirements for commencing the project. 2020, c. 18, Sched. 6, s. 30.
Restriction on provincial funding
(4) The Crown or a Crown agency shall not give a loan, grant, subsidy or guarantee with respect to the project until the proponent has satisfied the prescribed requirements for commencing the project. 2020, c. 18, Sched. 6, s. 30.
Exception
(5) Despite subsection (4), a loan, grant, subsidy or guarantee described in that subsection may be given with respect to an activity permitted by subsection (1) before the proponent has satisfied the prescribed requirements for commencing the project. 2020, c. 18, Sched. 6, s. 30.
Prohibition on projects that are proceeding
(6) No person shall issue a document described in subsection (2) or give a loan, grant, subsidy or guarantee described in subsection (4) with respect to a Part II.4 project after the prescribed requirements for commencing the project have been satisfied if doing so would be contrary to,
(a) a prescribed requirement for proceeding with the project; or
(b) a requirement imposed in an order of the Minister under subsection 17.31 (3). 2020, c. 18, Sched. 6, s. 30.
Order to comply with Part II.3
17.31 (1) The Minister may make an order declaring a Part II.4 project to be a Part II.3 project for the purposes of this Act. 2020, c. 18, Sched. 6, s. 30.
Same
(2) In an order under subsection (1), the Minister may do the following:
1. Set out directions with respect to the terms of reference governing the preparation of an environmental assessment under Part II.3 for the project.
2. Declare that the proponent has satisfied such requirements for the preparation of an environmental assessment under Part II.3 as are specified in the order. 2020, c. 18, Sched. 6, s. 30.
Same, additional requirements
(3) The Minister may by order impose requirements on a Part II.4 project in addition to any prescribed requirements for commencing or proceeding with the project. 2020, c. 18, Sched. 6, s. 30.
Same
(4) An order under subsection (1) or (3) may be made on the initiative of the Minister or on the request of a person under subsection (7). 2020, c. 18, Sched. 6, s. 30.
Prescribed limits
(5) The Minister shall not make an order under subsection (1) or (3) on his or her own initiative after the prescribed deadline. 2020, c. 18, Sched. 6, s. 30.
Basis for order
(6) The Minister shall consider the following matters when making an order under this section:
1. The purpose of this Act.
2. The factors suggesting that the proposed Part II.4 project differs from other Part II.4 projects of the same type.
3. The significance of the factors and of the differences mentioned in paragraph 2.
4. If a request for the order was made by a person under subsection (7), any ground for making the request that is given by that person and permitted under subsection (7).
5. The mediators’ report, if any, following a referral under subsection (10).
6. Such other matters as may be prescribed.
7. Such other matters as the Minister considers appropriate. 2020, c. 18, Sched. 6, s. 30.
Request for order
(7) A person may request the Minister to make an order under this section only on the grounds that the order may prevent, mitigate or remedy adverse impacts on the existing aboriginal and treaty rights of the aboriginal peoples of Canada as recognized and affirmed in section 35 of the Constitution Act, 1982. 2020, c. 18, Sched. 6, s. 30.
Same
(8) A request under subsection (7) shall be made in the form and manner that may be specified by the Director and shall include such information as may be specified by the Director. 2020, c. 18, Sched. 6, s. 30.
Same
(9) If a request is made under subsection (7) with respect to a project, no person shall proceed with the project until such time as,
(a) the Minister has made a decision with respect to the request; or
(b) the Minister has given a notice to the proponent stating that the proponent may proceed with the project. 2020, c. 18, Sched. 6, s. 30.
Mediation
(10) The Minister may refer a matter in connection with a request to mediation and section 17.14 applies with necessary modifications. 2020, c. 18, Sched. 6, s. 30.
Order after request
(11) For the purpose of considering a request made by a person under subsection (7), the Director may require the proponent to undertake such consultations and to provide such information as the Director may specify. 2020, c. 18, Sched. 6, s. 30.
Refusal after request
(12) If, after receiving a request under subsection (7), the Minister refuses to make an order, the Minister shall notify the person who made the request of his or her decision and shall give the person reasons for the decision. 2020, c. 18, Sched. 6, s. 30.
Notice of order
(13) The Minister shall give a copy of an order under this section, together with the reasons for it, to the proponent, to the person, if any, who requested an order and to such other persons as the Minister considers advisable. 2020, c. 18, Sched. 6, s. 30.
Change to project
(14) If a proponent of a Part II.4 project wishes to make a change to the project after it has satisfied the prescribed requirements for commencing the project, the Minister may make an order under this section with respect to the change and this section shall apply with necessary modifications to such an order. 2020, c. 18, Sched. 6, s. 30.
Amendment of subs. (3) order
(15) The Minister may, in accordance with the regulations, if any, amend any order made under subsection (3), regardless of whether the order was made before or after section 30 of Schedule 6 to the COVID-19 Economic Recovery Act, 2020 came into force. 2020, c. 18, Sched. 6, s. 30.
Read the Environmental Assessment Act on e-Laws ↗