Drainage Act, R.S.O. 1990, c. D.17
Section 9
Determination of petition compliance
Cite as Drainage Act, R.S.O. 1990, c. D.17, s. 9 · current to November 11, 2026 · consolidated from June 30, 2021 · read from e-Laws on November 17, 2026
The text
(1) The engineer shall, before making an examination and report, cause the clerk of the local municipality to send at least seven days notice in the form prescribed by the regulations to each owner of lands within the area requiring drainage as described in the petition and to each public utility that may be affected by the petition setting out the time and place of an on-site meeting with the engineer to examine the area. R.S.O. 1990, c. D.17, s. 9 (1); 2010, c. 16, Sched. 1, s. 2 (5).
(2) At the on-site meeting, the engineer shall,
(a) determine the area requiring drainage;
(b) determine whether the petition complies with section 4 for the area requiring drainage; and
(c) where the engineer is of opinion that the petition fails to so comply, establish the requirements for a petition to comply with section 4. R.S.O. 1990, c. D.17, s. 9 (2).
(3) Where the engineer is of opinion that the petition complies with section 4, the engineer shall proceed to prepare a report or a preliminary report, as the case may be. R.S.O. 1990, c. D.17, s. 9 (3).
(4) Where the engineer is of opinion that the petition does not comply with section 4, the engineer shall so report to the council of the initiating municipality stating wherein the petition is deficient, the amount of the engineer’s fees and by whom they shall be paid, and the council shall forthwith send a copy of such opinion to each petitioner. R.S.O. 1990, c. D.17, s. 9 (4).
(5) Where, within sixty days of the engineer’s reporting to council under subsection (4), a petition that complies with the requirements of section 4 is filed with the clerk of the council,
(a) the council shall instruct the engineer to prepare a report, or a preliminary report, as the case may be; and
(b) the fees mentioned in subsection (4) shall form part of the cost of the drainage works. R.S.O. 1990, c. D.17, s. 9 (5).
Read the Drainage Act on e-Laws ↗