(1) Where the council of an initiating municipality has adopted a report for the construction of a drainage works after the time for appealing has expired and there are no appeals or after all appeals have been decided, the council may pass the provisional by-law to which the engineer’s report was attached, thereby authorizing the construction of the drainage works, and work may be commenced ten days after the by-law is passed if no notice of intention to make application to quash the by-law has been filed with the clerk of the council. R.S.O. 1990, c. D.17, s. 58 (1); 2010, c. 16, Sched. 1, s. 2 (23).
(2) If no notice of intention to make application to quash a by-law is filed with the clerk of the council within ten days after the passing of the by-law or, where a notice of intention has been given, if an application to quash is not made to the referee within three months after the passing of the by-law, the by-law, or so much thereof as is not the subject of or is not quashed upon any such application, is valid and binding according to its terms, so far as it prescribes or directs anything within the proper competence of the council. R.S.O. 1990, c. D.17, s. 58 (2).
(3) A by-law may be repealed at any time before the work is commenced and before any assessment has been levied against the land assessed, and in such case the council of the initiating municipality shall pay all expenses in connection therewith out of the general funds of the municipality. R.S.O. 1990, c. D.17, s. 58 (3).
(4) If, at any time after the by-law is passed and before any assessments are levied, a gross error in the report is found, the council of the initiating municipality may on notice to all persons assessed apply to the Tribunal to correct the error. R.S.O. 1990, c. D.17, s. 58 (4); 2006, c. 19, Sched. A, s. 6 (1).
(5) Where the council does not proceed with reasonable dispatch with the construction of the work after passage of the by-law, a petitioner may appeal to the Tribunal or, where lands used for agricultural purposes are included in the area to be drained, the Minister may refer the matter to the Tribunal, and the Tribunal may direct the council to take such action as the council is authorized to take under this Act and as the Tribunal considers proper. R.S.O. 1990, c. D.17, s. 58 (5); 2006, c. 19, Sched. A, s. 6 (1); 2010, c. 16, Sched. 1, s. 2 (24).