Construction Act, R.S.O. 1990, c. C.30
Section 87.3
Transition, Construction Lien Amendment Act, 2017
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 87.3 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) This Act and the regulations, as they read on June 29, 2018, continue to apply with respect to an improvement if,
(a) a contract for the improvement was entered into before July 1, 2018;
(b) a procurement process for the improvement was commenced before July 1, 2018 by the owner of the premises; or
(c) in the case of a premises that is subject to a leasehold interest that was first entered into before July 1, 2018, a contract for the improvement was entered into or a procurement process for the improvement was commenced on or after July 1, 2018 and before the day subsection 19 (1) of Schedule 8 to the Restoring Trust, Transparency and Accountability Act, 2018 came into force. 2018, c. 17, Sched. 8, s. 19 (1).
(2) For greater certainty, clauses (1) (a) and (c) apply regardless of when any subcontract under the contract was entered into. 2018, c. 17, Sched. 8, s. 19 (1).
(3) Despite subsection (1), the amendments made to this Act by subsections 13 (4), 14 (4) and 29 (2) and (4) of the Construction Lien Amendment Act, 2017 apply with respect to an improvement to a premises in which a municipality has an interest, even if a contract for the improvement was entered into or a procurement process for the improvement was commenced before July 1, 2018. 2018, c. 17, Sched. 8, s. 19 (2).
(4) Parts I.1 and II.1 do not apply with respect to the following contracts and subcontracts:
1. A contract entered into before the day subsection 11 (1) of the Construction Lien Amendment Act, 2017 came into force.
2. A contract entered into on or after the day subsection 11 (1) of the Construction Lien Amendment Act, 2017 came into force, if a procurement process for the improvement that is the subject of the contract was commenced before that day by the owner of the premises.
3. A subcontract made under a contract referred to in paragraph 1 or 2. 2018, c. 17, Sched. 8, s. 19 (3).
Read the Construction Act on e-Laws ↗