Construction Act, R.S.O. 1990, c. C.30
Section 77
Priority of liens over executions, etc.
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 77 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
The liens arising from an improvement have priority over all judgments, executions, assignments, attachments, garnishments and receiving orders except those executed or recovered upon before the time when the first lien arose in respect of the improvement. R.S.O. 1990, c. C.30, s. 77.
Read the Construction Act on e-Laws ↗