Construction Act, R.S.O. 1990, c. C.30
Section 6.4
Payment deadline, owner to contractor
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 6.4 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) Subject to the giving of a notice of non-payment under subsection (2), an owner shall pay the amount payable under a proper invoice no later than 28 days after receiving the proper invoice from the contractor. 2017, c. 24, s. 7.
(2) An owner who disputes a proper invoice may refuse to pay all or any portion of the amount payable under the proper invoice within the time specified in subsection (1) if, no later than 14 days after receiving the proper invoice from the contractor, the owner gives to the contractor a notice of non-payment, in the prescribed form and manner, specifying the amount of the proper invoice that is not being paid and detailing all of the reasons for non-payment. 2017, c. 24, s. 7.
(3) Subsection (1) continues to apply to any amount payable under the proper invoice that is not the subject of a notice under subsection (2). 2017, c. 24, s. 7.
Read the Construction Act on e-Laws ↗