The text
(1) No certificate, declaration or claim for lien is invalidated by reason only of a failure to comply strictly with subsection 32 (2), 33 (1) or 34 (5) unless, in the opinion of the court, a person has been prejudiced as a result, and then only to the extent of the prejudice suffered. 2017, c. 24, s. 6 (2); 2018, c. 17, Sched. 8, s. 2.
(2) Minor errors or irregularities to which subsection (1) applies include,
(a) a minor error or irregularity in,
(i) the name of an owner, a person for whom services or materials were supplied or a payment certifier,
(ii) the legal description of a premises, or
(iii) the address for service; and
(b) the placement of an owner’s name in the wrong portion of a claim for lien. 2017, c. 24, s. 6 (2); 2024, c. 20, Sched. 4, s. 4.