Construction Act, R.S.O. 1990, c. C.30
Section 47
Power to discharge
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 47 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) The court may, on motion, order the discharge of a lien,
(a) on the basis that the claim for the lien is frivolous, vexatious or an abuse of process; or
(b) on any other proper ground. 2017, c. 24, s. 37 (1).
(1.1) The court may, on motion, make any of the following orders, on any proper ground:
1. An order that the registration of a claim for lien, a certificate of action or both be vacated.
2. If written notice of a lien has been given, a declaration that the lien has expired or that the written notice of the lien shall no longer bind the person to whom it was given.
3. An order dismissing an action. 2017, c. 24, s. 37 (1); 2018, c. 17, Sched. 8, s. 15 (1).
(1.2) An order under subsection (1) or (1.1) may include any terms or conditions that the court considers appropriate in the circumstances. 2017, c. 24, s. 37 (1).
(2) Where a certificate of action is vacated under paragraph 1 of subsection (1.1), and there remain liens which may be enforced in the action to which that certificate relates, the court shall give any directions that are necessary in the circumstances in respect of the continuation of that action subject to paragraph 4 of subsection 44 (9). R.S.O. 1990, c. C.30, s. 47 (2); 2010, c. 16, Sched. 2, s. 2 (13); 2017, c. 24, s. 37 (2); 2018, c. 17, Sched. 8, s. 15 (2).
Read the Construction Act on e-Laws ↗