How holdback not to be applied

Cite as Construction Act, R.S.O. 1990, c. C.30, s. 30 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026

The text

If a contract or subcontract is abandoned or terminated, a holdback shall not be applied by any payer toward obtaining services or materials in substitution for those that were to have been supplied under the contract or subcontract, nor in payment or satisfaction of any claim against the contractor or subcontractor, until all liens that may be claimed against that holdback have expired or been satisfied, discharged or otherwise provided for under this Act. 2025, c. 14, Sched. 2, s. 5.