Construction Act, R.S.O. 1990, c. C.30
Section 22
Basic holdback
Cite as Construction Act, R.S.O. 1990, c. C.30, s. 22 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 17, 2026
The text
(1) Each payer upon a contract or subcontract under which a lien may arise shall retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied under the contract or subcontract until all liens that may be claimed against the holdback in respect of the supplied services or materials have expired or been satisfied, discharged or otherwise provided for under this Act. R.S.O. 1990, c. C.30, s. 22 (1); 2017, c. 24, s. 17 (1), 66; 2024, c. 20, Sched. 4, s. 25.
(2) Where the contract has been certified or declared to be substantially performed but services or materials remain to be supplied to complete the contract, the payer upon the contract, or a subcontract, under which a lien may arise shall retain, from the date certified or declared to be the date of substantial performance of the contract, a separate holdback equal to 10 per cent of the price of the remaining services or materials as they are actually supplied under the contract or subcontract, until all liens that may be claimed against the holdback have expired or been satisfied, discharged or otherwise provided for under this Act. R.S.O. 1990, c. C.30, s. 22 (2); 2017, c. 24, s. 17 (2), 66.
(3) The obligation to retain the holdbacks under subsections (1) and (2) applies irrespective of whether the contract or subcontract provides for partial payments or payment on completion. R.S.O. 1990, c. C.30, s. 22 (3).
(4) Some or all of any holdbacks may, instead of being retained in the form of funds, be retained in one or more of the following forms:
1. A letter of credit in the prescribed form.
2. A demand-worded holdback repayment bond in the prescribed form.
3. Any other form that may be prescribed. 2017, c. 24, s. 17 (3).